An electric machine is configured with at least two sets of phase windings. A plurality of power switches is configured to selectively couple voltage terminals to each of the phase windings. A controller is programmed to operate the power switches according to a switching pattern, for each of the sets, updated at intervals defined by a switching frequency such that the switching patterns are different during each one of the intervals.
|
8. A method for operating an electric machine having at least two sets of three phase windings comprising:
operating, by a controller, a plurality of power switches configured to selectively couple voltage terminals to each of the phase windings according to a switching pattern, for each of the sets, updated at intervals and defined such that the switching patterns are different and achieve a same reference voltage vector during each one of the intervals.
13. An electrified powertrain comprising;
an electric machine configured with at least two sets of phase windings;
a plurality of power switches configured to selectively couple voltage terminals to each of the phase windings; and
a controller programmed to operate the power switches during an interval according to a sequence of space vector modulation states, for each of the sets, that defines a different zero vector pattern for each of the sets during the interval.
1. A vehicle comprising:
an electric machine configured with at least two sets of three phase windings;
a plurality of power switches configured to selectively couple voltage terminals to each of the phase windings; and
a controller programmed to operate the power switches according to a switching pattern, for each of the sets, updated at intervals defined by a switching frequency and defined so that each of the sets achieves a same reference voltage vector using switching patterns that are different during each one of the intervals.
2. The vehicle of
3. The vehicle of
4. The vehicle of
5. The vehicle of
6. The vehicle of
7. The vehicle of
9. The method of
10. The method of
11. The method of
12. The method of
14. The electrified powertrain of
15. The electrified powertrain of
16. The electrified powertrain of
17. The electrified powertrain of
18. The electrified powertrain of
19. The electrified powertrain of
|
This application is generally related to a control system for a multiple inverter system for driving an electric machine in an electrified vehicle.
Electrified vehicles including hybrid-electric vehicles (HEVs) and battery electric vehicles (BEVs) rely on a traction battery to provide power to a traction motor for propulsion and a power inverter therebetween to convert direct current (DC) power to alternating current (AC) power. The typical AC traction motor is a three-phase motor that may be powered by three sinusoidal signals each driven with 120-degree phase separation. The traction battery is configured to operate in a particular voltage range and provide a maximum current. The traction battery is alternatively referred to as a high-voltage battery. However, improved performance of electric machines may be achieved by operating in a different voltage range, typically at voltages greater than the traction battery terminal voltage. Likewise, the current requirements to drive a vehicular electric machine are commonly referred to as high current.
Also, many electrified vehicles include a DC-DC converter, also referred to as a variable voltage converter (VVC), to convert the voltage of the traction battery to an operational voltage level of the electric machine. The electric machine, that may include a traction motor and a generator, may require high voltage and high current. Due to the voltage and current requirements, a battery module and a power electronics module are typically in continuous communication. The battery module provides information for the vehicle control algorithms including battery voltage, battery current, and battery state-of-charge (SOC).
A vehicle includes an electric machine configured with at least two sets of phase windings. The vehicle further includes a plurality of power switches configured to selectively couple voltage terminals to each of the phase windings. The vehicle further includes a controller programmed to operate the power switches according to a switching pattern, for each of the sets, updated at intervals defined by a switching frequency such that the switching patterns are different during each one of the intervals.
A method for operating an electric machine having at least two sets of phase windings includes operating, by a controller, a plurality of power switches configured to selectively couple voltage terminals to each of the phase windings according to a switching pattern, for each of the sets, updated at intervals defined by a switching frequency such that the switching patterns are different during each one of the intervals.
An electrified powertrain includes an electric machine configured with at least two sets of phase windings. The electrified powertrain further includes a plurality of power switches configured to selectively couple voltage terminals to each of the phase windings. The electrified powertrain further includes a controller programmed to operate the power switches during an interval according to a sequence of space vector modulation states, for each of the sets, that defines a different zero vector pattern for each of the sets during the interval.
Embodiments of the present disclosure are described herein. It is to be understood, however, that the disclosed embodiments are merely examples and other embodiments can take various and alternative forms. The figures are not necessarily to scale; some features could be exaggerated or minimized to show details of particular components. Therefore, specific structural and functional details disclosed herein are not to be interpreted as limiting, but merely as a representative basis for teaching one skilled in the art to variously employ the present invention. As those of ordinary skill in the art will understand, various features illustrated and described with reference to any one of the figures can be combined with features illustrated in one or more other figures to produce embodiments that are not explicitly illustrated or described. The combinations of features illustrated provide representative embodiments for typical applications. Various combinations and modifications of the features consistent with the teachings of this disclosure, however, could be desired for particular applications or implementations.
A voltage level of the energy storage unit 2 may differ from an input voltage for the power conversion units 4, 6 and a DC-DC converter also referred to as a Variable Voltage Converter (VVC) may be electrically coupled between the power conversion units 4, 6 and the energy storage unit 2. For example, consider an energy storage unit 2 that has a voltage of 200V and an electric drive 8 that requires 120 kW of power to provide propulsion. A power conversion unit input bus may be configured to provide 400V at 300 A or 200V at 600 A to produce the required 120 kW electric drive power. An electric drive unit 8 may be configured to accommodate different input voltages at which to operate. However, the choice of which input voltage to select may be limited by power electronics devices of the power conversion units 4, 6. For example, if a 200V energy storage unit 2 is directly connected to a 200V/600 A DC bus, the power switches of the power conversion units 4, 6 have to operate at 200V/600 A. This voltage/current combination may be cost prohibitive as the high current requirement at the lower voltage may not be economical as the power switches with those specifications may be expensive. In comparison, power switches that operate at 400V/300 A may be more cost-effective. To match the 200V input voltage and desired 400V DC bus voltage, a DC/DC converter (e.g., VVC) may be used to boost the voltage from 200V to 400V. The use of the VVC adds extra power switches and inductors to the electrified powertrain, thereby increasing size and cost. In addition, a VVC is typically connected as a cascaded-connection in the power circuit and hence power loss is generated twice during both energy storage unit charging and discharging cycles. This induces extra power loss and reduces vehicle fuel economy.
To reduce cost and improve packaging for the electrified powertrain, it is desirable to eliminate the DC/DC converter (e.g., VVC). However, a practical and economic way to provide the power requirement without having the cost of high current components (e.g., 200V/600 A components for a 120 kW inverter) is needed. One solution is to implement a parallel power conversion module structure that divides the energy storage unit power to sections of an electric machine. The power flows in windings around stator teeth to induce a field within the stator teeth. This electrified powertrain configuration is such that each power conversion module 4,6 is used to focus a field in stator teeth that reside exclusively in a single section of the electric machine. For example, a power conversion module system bifurcates the power to a first and second power conversion module. The first power conversion module 4 only supplies power to windings around stator teeth in a first section of the electric machine, while the second power conversion module 6 only supplies power to windings around stator teeth in a second section of the electric machine. Here, the first section of the electric machine may be a first half of the electric machine, and the second section of the electric machine may be a second half of the electric machine. The sections of the electric machine are defined by a plane that is coincident with an axis of rotation of the electric machine.
A traction battery or battery pack 124 stores energy that can be used by the electric machines 114. The traction battery 124 may provide a high-voltage direct current (DC) output. The traction battery 124 may be electrically coupled to one or more power electronics modules 126. One or more contactors 142 may isolate the traction battery 124 from other components when opened and connect the traction battery 124 to other components when closed. The power electronics module 126 is also electrically coupled to the electric machines 114 and provides the ability to bi-directionally transfer energy between the traction battery 124 and the electric machines 114. For example, a traction battery 124 may provide a DC voltage while the electric machines 114 may operate with a three-phase alternating current (AC) to function. The power electronics module 126 may convert the DC voltage to a three-phase AC current to operate the electric machines 114. In a regenerative mode, the power electronics module 126 may convert the three-phase AC current from the electric machines 114 acting as generators to the DC voltage compatible with the traction battery 124.
The vehicle 112 may include a variable-voltage converter (VVC) 152 electrically coupled between the traction battery 124 and the power electronics module 126. The VVC 152 may be a DC/DC boost converter configured to increase or boost the voltage provided by the traction battery 124. By increasing the voltage, current requirements may be decreased leading to a reduction in wiring size for the power electronics module 126 and the electric machines 114. Further, the electric machines 114 may be operated with better efficiency and lower losses.
In addition to providing energy for propulsion, the traction battery 124 may provide energy for other vehicle electrical systems. The vehicle 112 may include a DC/DC converter module 128 that converts the high-voltage DC output of the traction battery 124 to a low voltage DC supply that is compatible with low-voltage vehicle loads. An output of the DC/DC converter module 128 may be electrically coupled to an auxiliary battery 130 (e.g., 12V battery) for charging the auxiliary battery 130. The low-voltage systems may be electrically coupled to the auxiliary battery 130. One or more electrical loads 146 may be coupled to the high-voltage bus. The electrical loads 146 may have an associated controller that operates and controls the electrical loads 146 when appropriate. Examples of electrical loads 146 may be a fan, an electric heating element and/or an air-conditioning compressor.
The electrified vehicle 112 may be configured to recharge the traction battery 124 from an external power source 136. The external power source 136 may be a connection to an electrical outlet. The external power source 136 may be electrically coupled to a charger or electric vehicle supply equipment (EVSE) 138. The external power source 136 may be an electrical power distribution network or grid as provided by an electric utility company. The EVSE 138 may provide circuitry and controls to regulate and manage the transfer of energy between the power source 136 and the vehicle 112. The external power source 136 may provide DC or AC electric power to the EVSE 138. The EVSE 138 may have a charge connector 140 for plugging into a charge port 134 of the vehicle 112. The charge port 134 may be any type of port configured to transfer power from the EVSE 138 to the vehicle 112. The charge port 134 may be electrically coupled to a charger or on-board power conversion module 132. The power conversion module 132 may condition the power supplied from the EVSE 138 to provide the proper voltage and current levels to the traction battery 124. The power conversion module 132 may interface with the EVSE 138 to coordinate the delivery of power to the vehicle 112. The EVSE connector 140 may have pins that mate with corresponding recesses of the charge port 134. Alternatively, various components described as being electrically coupled or connected may transfer power using a wireless inductive coupling.
One or more wheel brakes 144 may be provided for decelerating the vehicle 112 and preventing motion of the vehicle 112. The wheel brakes 144 may be hydraulically actuated, electrically actuated, or some combination thereof. The wheel brakes 144 may be a part of a brake system 150. The brake system 150 may include other components to operate the wheel brakes 144. For simplicity, the figure depicts a single connection between the brake system 150 and one of the wheel brakes 144. A connection between the brake system 150 and the other wheel brakes 144 is implied. The brake system 150 may include a controller to monitor and coordinate the brake system 150. The brake system 150 may monitor the brake components and control the wheel brakes 144 for vehicle deceleration. The brake system 150 may respond to driver commands and may also operate autonomously to implement features such as stability control. The controller of the brake system 150 may implement a method of applying a requested brake force when requested by another controller or sub-function.
Electronic modules in the vehicle 112 may communicate via one or more vehicle networks. The vehicle network may include a plurality of channels for communication. One channel of the vehicle network may be a serial bus such as a Controller Area Network (CAN). One of the channels of the vehicle network may include an Ethernet network defined by Institute of Electrical and Electronics Engineers (IEEE) 802 family of standards. Additional channels of the vehicle network may include discrete connections between modules and may include power signals from the auxiliary battery 130. Different signals may be transferred over different channels of the vehicle network. For example, video signals may be transferred over a high-speed channel (e.g., Ethernet) while control signals may be transferred over CAN or discrete signals. The vehicle network may include any hardware and software components that aid in transferring signals and data between modules. The vehicle network is not shown in
The VVC 152 may be configured as a boost converter. The VVC 152 may include input terminals that may be coupled to terminals of the traction battery 124 through the contactors 142. The VVC 152 may include output terminals coupled to terminals of the power electronics module 126. The VVC 152 may be operated to cause a voltage at the output terminals to be greater than a voltage at the input terminals. The vehicle 112 may include a VVC controller that monitors and controls electrical parameters (e.g., voltage and current) at various locations within the VVC 152. In some configurations, the VVC controller may be included as part of the VVC 152. The VVC controller may determine an output voltage reference, V*dc. The VVC controller may determine, based on the electrical parameters and the voltage reference, V*dc, a control signal sufficient to cause the VVC 152 to achieve the desired output voltage. In some configurations, the control signal may be implemented as a pulse-width modulated (PWM) signal in which a duty cycle of the PWM signal is varied. The control signal may be operated at a predetermined frequency. The VVC controller may command the VVC 152 to provide the desired output voltage using the control signal. The particular control signal at which the VVC 152 is operated may be directly related to the amount of voltage boost to be provided by the VVC 152.
With reference to
With reference to
As shown in
With continuing reference to
As illustrated in
Referring again to
The system may also include a speed and/or position feedback sensor 326 that is coupled to the electric machine 114. For example, the position feedback sensor 326 may be a resolver that outputs a signal indicative of an angle of rotation. The position feedback sensor 326 may output a signal that is received by the controller 310. The controller 310 may determine from the feedback signal an angle of rotation of the electric machine 114 and a rotational speed of the electric machine 114. The controller 310 may include interface circuitry to process, convert, scale, and/or filter the position feedback signal.
As shown in
As illustrated in
To control the switching configuration of the inverter 126, the inverter 126 changes the switching state of each power switch 302 in the inverter 126 to either an ON state or an OFF state based on the control signal 236. In the illustrated embodiment, to switch the power switch 302 to either ON or OFF states, the controller/LD 310 provides the gate voltage (Vg) to each power switch 302 and therefore drives the switching state of each power switch 302. Gate voltages Vga1, Vga2, Vgb1, Vgb2, Vgc1, and Vgc2 (shown in
As also shown in
Two situations can occur during an active state of the three-phase converter example illustrated in
Solid state devices (SSD), such as Insulated Gate Bipolar Junction Transistors (IGBTs), Metal Oxide Semiconductor Field Effect Transistors (MOSFETs), or Bipolar Junction Transistors (BJTs) are widely used in a variety of automotive and industrial applications, such as electric motor drives, power inverters, DC-DC converters, and power modules. Operation of an IGBT and a MOSFET is voltage controlled, in which the operation is based on a voltage applied to a gate of the IGBT or MOSFET, while operation of a BJT is current controlled, in which the operation is based on a current applied to a base of the BJT. Here, the use of SSDs or high-power relays may be used to control, alter, or modulate a current between a battery and an electric machine of a vehicle.
The controller 310 for the inverter 126 may be programmed to implement a switching control strategy for the power switches 302. Different switching control strategies for operating the power switches 302 are available. The methods may be characterized as PWM switching patterns and non-PWM switching patterns. PWM switching patterns utilize a PWM signal at the gate drives of the power switches 302. Examples of PWM switching patterns includes Space Vector PWM (SVPWM) and Discontinuous PWM (DPWM). Examples of non-PWM switching patterns include Six-Step control and Selected Harmonic Elimination (SHE). The switching strategies have different characteristics with respect to noise and switching losses. In addition, the switching frequency of the control signals may be constrained with some switching strategies. SVPWM may be characterized by low noise but large losses. DPWM switching strategies may be characterized by medium noise and loss levels. Six-Step switching strategies may be characterized by large amounts of noise and small losses. SHE switching strategies may be characterized by low losses and medium loss levels. A typical design goal for an inverter is to minimize both noise and losses to the extent possible. Selection of the switching strategy generally defines the noise and loss characteristics that will be achieved.
In a multi-three-phase (MTP) system that uses multiple inverters to control a single electric machine, there may be flexibility in the selection of the switching strategy for each of the inverters. As discussed, the switching control strategies provide differing levels of compromise between noise and loss levels. In the case of the MTP system, more than one inverter is operating to control the additional phase legs of the electric machine. One choice is to control each set of phase legs with the same control strategy. That is, generate the same switching pattern for each of the sets of phase legs. In this case, any electromagnetic noise generated will be the same for each of the sets of phase legs. To change the noise characteristics, the sets of phase legs may be controlled to achieve the same reference voltage vector but a different switching pattern may be applied. For example, the order of application of the switching states may be reversed for one of the inverters. The result is that the same voltage may be achieved but in a slightly different manner. Rates of change of the current and voltage within each of the intervals may be different between the inverters. This may cause a difference in noise characteristics between each of the inverters. Using a common switching strategy for the inverters constrains the system to accept the constraints inherent with the selected strategy. However, by operating each inverter with a different switching control strategy, the system may achieve improvements in audible noise, current ripple and vibration.
Control strategies that operate each of the inverters in a different manner may reduce noise signatures. In some configurations, each of the inverters may use a SVPWM strategy in which each inverter operates at a different switching frequency. In some configurations, one of the inverters may be controlled using a six-step control strategy, while another of the inverters may be controlled using the SVPWM strategy. In some configurations, the SVPWM controlled inverter may be modified to generate a noise compensation waveform to compensate for noise generated by the six-step controlled inverter. In some configurations, the inverters may be controlled using PWM strategies operating at the same switching frequency. For example, one inverter may operate using the SVPWM strategy while another operates using the DPWM strategy. The result is that each inverter generates a different noise signature that may be spread out over the frequency spectrum at a lower amplitude.
A three-phase AC electric machine is operated by applying a three-phase alternating current to the phase windings. Referring to
From a controls prospective, manipulating the three-phase quantities for control purposes is cumbersome. To improve this situation, various methods have been developed to simplify control strategies. Vector control strategies are based on transforming the alternating three-phase signals into a two-dimensional DC signals by using coordinate transformations. A first transformation may be used to transform the three-phase signals into a two-dimensional space. Control operations may be performed in the two-dimensional coordinate system. A second transformation may be used to output the control signals in three-dimensional coordinate system. A reference voltage or current vector for the electric machine may be represented as a two-dimensional vector having an α-axis 702 and a β-axis 704. The two axes define the vector space.
Typical control strategies for electric machines include space vector modulation strategies. Space vector modulation strategies may operate by determining a reference voltage or current vector in the two-dimensional vector space. The reference vector may be computed based on a desired torque and speed of the electric machine. The space vector modulation strategy may operate by defining switching patterns or vectors based on combinations of states of the power switches 302. Within the two dimensional-space, certain vectors may be defined corresponding to various combinations of switching states of the power switches 302.
Vectors representing particular switching states may be represented in the vector space 700 as depicted in
TABLE 1
Switch
State
302A
302B
302C
302D
302E
302F
(100)
on
off
off
off
on
on
(110)
on
on
off
off
off
on
(010)
off
on
off
on
off
on
(011)
off
on
on
on
off
off
(001)
off
off
on
on
on
off
(101)
on
off
on
off
on
off
(000)
off
off
off
on
on
on
(111)
on
on
on
off
off
off
A second vector, u2 714 may be defined having a switching state of (110). A third vector, u3, 716 may be defined having a switching state of (010). A fourth vector, u4, 718 may be defined along the negative of the α-axis 702 having a switching state of (011). A fifth vector, u5, 720 may be defined having a switching state of (001). A sixth vector, u6 722 may be defined having a switching state of (101). The vectors u1 through u6 may be referred to as active vectors. A first zero vector, u0, 724 may be defined having a switching state of (000). A second zero vector, u7, 726 may be defined having a switching state of (111). The first zero vector 724 and the second zero vector 726 have all phase legs/windings coupled to a common DC bus conductor.
The reference current/voltage may be represented in the vector space as some combination of the above defined vectors. The reference may be represented as a vector having a magnitude and an angle (relative to the α-axis 702) in the vector space. The reference vector may rotate in the vector space as a function of the rotational speed of the electric machine. The reference vector angle may be a function of the rotational angle of the electric machine. The magnitude of the vector may depend on a torque magnitude. The reference vector may be formed from a combination of the above defined vectors. Knowing the magnitude and angle of the vector allows a combination of the above defined vectors to be determined.
The space vector modulation strategy may select the two closest active vectors to the reference vector. In addition, an amount of time that each of the active vectors is applied is determined. The two closest active vectors may be those active vectors that the reference vector, V, 750 lies between. As the reference vector 750 rotates in the vector space, a different pair of active vectors will be used over the course of a full rotation. The application time for each of the applied vectors may be relative to an interval defined by the switching frequency (e.g., period defined by a predetermined frequency). The switching frequency defines the rate at which the states of the power switches 302 change. A switching period may be defined as the inverse of the switching frequency. The controller 310 may compute the proportion of the switching period that is allocated to each of the active vectors and zero vectors. The proportion of the switching period allocated to each of the active vectors depends on the magnitudes of the reference vector, V, 750, and the magnitudes of the component vectors v1 752 and v2 754. The proportion of the switching period allocated to each of the active vectors also depends on the relative angle of the reference vector V 750 within the vector space (e.g., angle between V 750 and the α-axis 702).
Once the application duration for each of the active vectors is computed, any remaining time within the interval may be filled by application of one or both of the zero vectors for the remaining time within the switching period. As a result, the power switches 302 for each leg of the electric machine may be switched on for a time defined by the space vector modulation strategy.
The state of the power switches may be output at each switching period. To achieve vectors of various magnitudes, a combination of active vectors and zero vectors is applied over each of the switching periods. As the magnitude of the reference vector, V, 750 decreases, larger proportions of the switching period may be allocated to the zero vectors. The switching frequency may define the rate at which the switching pattern is output by the inverter. The switching pattern may be updated at the switching frequency. In some configurations, the switching pattern may be updated at an integer multiple of the switching period (e.g., inverse of switching frequency). In such a case, the switching pattern may be changed at the integer multiple and then output over the next integer multiple of switching periods.
For each of the intervals, two or more actives states are applied for the associated application times depending on which vectors (ux defined above) that the reference vector, V 750, lies between. The active states and zero states may be applied in any order for the corresponding application times to achieve the reference voltage vector 750. In some applications, the pattern of active and zero vectors may be ordered such that only one of the power switches 302 changes at each transition. Such a selection may help to reduce switching losses.
In the MTP system, more than one inverter is operating to control the additional phase legs of the electric machine. For example, referring to
A first technique for applying a different switching pattern for each of the sets of windings is to change the order of the switch states between the inverters. To achieve, the same reference vector, the same vectors and application times may be selected. The switching states may be applied differently for each of the inverters over each switching interval. For example, the order of the switching states may be applied in a reversed order from one another. The net effect is to achieve the same reference vector but the switching patterns are different. As such, the audible noise characteristics of each machine will be different. If the same switching pattern is used, the audible noise characteristics would be the same and the effect may be additive. That is, more audible noise may be perceived when the same switching pattern is used. By using the different switching patterns, the noise spectrum may be spread out leading to a lower amplitude of noise.
A second switching pattern 802 may be defined for the second set of windings (e.g., 524 of
One difference between the first switching pattern 800 and the second switching pattern 802 is that the zero vectors are applied differently between the patterns. Once the zero vector duration is computed for a switching interval, the controller must determine how to allocate the zero vector duration between the zero vectors. Typical allocations are to divide the zero vector duration to a first interval at the beginning of the switching interval and a second interval at the end of the switching interval. Some control strategies (e.g., DPWM) may allocate the entire zero vector duration to one of the zero vectors.
A second switching pattern 852 may be defined for the second set of windings (e.g., 524 of
One difference between the first switching pattern 850 and the second switching patter 852 is that each of the patterns utilize a different number of zero vectors within each of the switching intervals 812. For example, the first switching pattern 850 may be derived from a SVPWM strategy and the second switching pattern 852 may be derived from a DPWM strategy. Both patterns achieve the same reference vector but the power switches 302 are switched using a different sequence. The result is that the noise characteristics of each set of phase windings is different. Such operation leads to a different audible noise characteristic when compared to switching the sets of phase windings with the same switching pattern.
Note that subsequent switching intervals are processed in a similar manner. The reference vector 750 will rotate in the vector space. As the reference vector 750 rotates, different pairs of active vectors will be selected. In subsequent intervals, the switching states and corresponding durations may change as reference vector rotates.
The controller 310 may be programmed to operate the power switches 302 for each of the sets according to a switching pattern derived for each of the sets as described. The switching pattern may be updated at intervals defined by the switching frequency. To reduce noise, the controller 310 may be programmed to select switching patterns for each set of power switches 302 that are different from one another. That is, the power switches associated with each set of phase windings are controlled with a different switching pattern over each of the intervals. The switching pattern is considered different when the switching patterns utilize a different sequence during an interval defined by the switching frequency. The switching patterns are not considered different if the same sequence is shifted in time (e.g., phase shift of one pattern relative to another).
The switching pattern defines a sequence of operating states for each of the power switches corresponding to each one of the sets. The switching pattern also defines durations for each of the operating states. The switching patterns may be selected to achieve the same average current or voltage over the interval in each of the set of phase windings. The switching pattern states and durations are used to control the gate drives to the power switches to control the voltage and current of each of the sets of phase windings.
The controller 310 may be programmed to differentiate the switching patterns based on selection of the zero vectors in each of the intervals. The zero vectors correspond to those switching states in which all of the power switches are operated to couple all of the phase windings associated with a set to a common voltage terminal for a duration. One way to differentiate the switching patterns is to utilize a different zero vector for each of the sets within an interval. In addition, a different sequence of zero vectors may be used. For example, the zero vectors may be applied such that each set does not output the same zero vector at the same time. Another way to differentiate the switching patterns is to utilize a different number of zero vectors for each of the sets of phase windings. For example, one sets may use one zero vector while another set may use both zero vectors during the same interval.
A goal of the inverter and electric machine operational strategy is to minimize an amount of audible noise that is produced by the drivetrain. The audible noise emitted by the electrified powertrain may be influenced by frequency of operation of the inverter. That is, the frequency over which the PWM signals operate. In addition, the switching patterns within the intervals defined by the inverse of the frequency can also influence the audible noise. For example, operating two inverters using the exact same switching patterns can cause an additive effect to the audible noise. Both inverters may be producing the same pattern of audible noise. By operating the inverters with different switching patterns within the intervals may cause differences in the patterns of audible noise generated by the inverters. By producing different audible noise patterns, the resulting summation of the audible noise may be less pronounced or spread over a wider spectrum at lower amplitude.
The processes, methods, or algorithms disclosed herein can be deliverable to/implemented by a processing device, controller, or computer, which can include any existing programmable electronic control unit or dedicated electronic control unit. Similarly, the processes, methods, or algorithms can be stored as data and instructions executable by a controller or computer in many forms including, but not limited to, information permanently stored on non-writable storage media such as Read Only Memory (ROM) devices and information alterably stored on writeable storage media such as floppy disks, magnetic tapes, Compact Discs (CDs), Random Access Memory (RAM) devices, and other magnetic and optical media. The processes, methods, or algorithms can also be implemented in a software executable object. Alternatively, the processes, methods, or algorithms can be embodied in whole or in part using suitable hardware components, such as Application Specific Integrated Circuits (ASICs), Field-Programmable Gate Arrays (FPGAs), state machines, controllers or other hardware components or devices, or a combination of hardware, software and firmware components.
While exemplary embodiments are described above, it is not intended that these embodiments describe all possible forms encompassed by the claims. The words used in the specification are words of description rather than limitation, and it is understood that various changes can be made without departing from the spirit and scope of the disclosure. As previously described, the features of various embodiments can be combined to form further embodiments of the invention that may not be explicitly described or illustrated. While various embodiments could have been described as providing advantages or being preferred over other embodiments or prior art implementations with respect to one or more desired characteristics, those of ordinary skill in the art recognize that one or more features or characteristics can be compromised to achieve desired overall system attributes, which depend on the specific application and implementation. These attributes may include, but are not limited to cost, strength, durability, life cycle cost, marketability, appearance, packaging, size, serviceability, weight, manufacturability, ease of assembly, etc. As such, embodiments described as less desirable than other embodiments or prior art implementations with respect to one or more characteristics are not outside the scope of the disclosure and can be desirable for particular applications.
Patent | Priority | Assignee | Title |
Patent | Priority | Assignee | Title |
6185115, | Nov 17 1998 | Three-phase pulse width modulation method and system for alternating current motor | |
6392905, | Jan 06 2001 | Ford Global Technologies, Inc. | Method and circuit for reducing battery ripple current in a multiple inverter system of an electrical machine |
7348757, | Jan 03 2005 | Infineon Technologies Americas Corp | Circuit to improve motor phase current reconstruction via DC link |
8248007, | Apr 15 2009 | Aisin Seiki Kabushiki Kaisha | Control apparatus and control method for AC motor |
8750009, | Dec 27 2007 | Mitsubishi Electric Corporation | Controller of a power converter that uses pulse width modulation |
9178455, | Dec 05 2012 | Robert Bosch GmbH | Control device and method for determining the rotor angle of a synchronous machine |
9214882, | Dec 05 2012 | Robert Bosch GmbH | Control device and method for determining the rotor angle of a synchronous machine |
20090277704, | |||
20150244301, | |||
20160105127, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Feb 06 2017 | WANG, JIYAO | Ford Global Technologies, LLC | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 041302 | /0629 | |
Feb 06 2017 | XU, WEI | Ford Global Technologies, LLC | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 041302 | /0629 | |
Feb 17 2017 | Ford Global Technologies, LLC | (assignment on the face of the patent) | / |
Date | Maintenance Fee Events |
Apr 12 2022 | M1551: Payment of Maintenance Fee, 4th Year, Large Entity. |
Date | Maintenance Schedule |
Nov 27 2021 | 4 years fee payment window open |
May 27 2022 | 6 months grace period start (w surcharge) |
Nov 27 2022 | patent expiry (for year 4) |
Nov 27 2024 | 2 years to revive unintentionally abandoned end. (for year 4) |
Nov 27 2025 | 8 years fee payment window open |
May 27 2026 | 6 months grace period start (w surcharge) |
Nov 27 2026 | patent expiry (for year 8) |
Nov 27 2028 | 2 years to revive unintentionally abandoned end. (for year 8) |
Nov 27 2029 | 12 years fee payment window open |
May 27 2030 | 6 months grace period start (w surcharge) |
Nov 27 2030 | patent expiry (for year 12) |
Nov 27 2032 | 2 years to revive unintentionally abandoned end. (for year 12) |