The invention is directed to a method for the construction of an industrial plant, in particular a petroleum refinery, by means of scaffolding units, each of which will be assembled from individual scaffolding components, comprising the following steps:
|
1. A method for the construction of an industrial plant, in particular a petroleum refinery, comprising the following steps:
selecting scaffolding units, each of which will be assembled from individual scaffolding components, the scaffolding components having at least one fixed dimension selected from: a height, a width, and a length;
providing a 3d construction plan in which building structures of the industrial plant are recorded in a computer-readable electronic format in a computer, the 3d construction plan being visualizable using software installed on the computer;
drawing the scaffolding units to be used for the construction of the industrial plant in the 3d construction plan of the industrial plant, the drawing being done using the software installed on the computer;
modifying the 3d construction plan with respect to at least one building structure of the industrial plant by revising the least one building structure to support the scaffolding units, the modifying being done using the software installed on the computer; and
building the industrial plant according to the modified construction plan and by using the scaffolding units drawn in the 3d construction plan.
2. A method for the construction of an industrial plant, in particular a petroleum refinery, comprising the following steps:
selecting scaffolding units, each of which will be assembled from individual scaffolding components, the scaffolding components having at least one fixed dimension selected from: a height, a width, and a length;
providing a 3d construction plan in which building structures of the industrial plant are recorded in a computer-readable electronic format in a computer, the 3d construction plan being visualizable using software installed on the computer;
drawing the scaffolding units to be used for the construction of the industrial plant in the 3d construction plan of the industrial plant, the drawing being done using the software installed on the computer;
modifying the 3d construction plan with respect to at least one building structure of the industrial plant by repositioning the least one building structure in order to use the scaffolding units to construct the building structure, the modifying being done using the software installed on the computer; and
building the industrial plant according to the modified construction plan and by using the scaffolding units drawn in the 3d construction plan.
3. Method according to
4. Method according to
5. Method according to
6. Method according to
7. Method according to
8. Method according to
9. Method according to
10. Method according to
11. Method according to
12. Method according to
13. Method according to
|
None.
The invention refers to a method for construction of an industrial plant, in particular a petroleum refinery.
The surface area of industrial plants generally covers up to several square miles, which necessitates to group the entire construction project into numerous sections, where construction work is done simultaneously and/or sequentially. For the construction of large-scale industrial plants such as petroleum refineries or other types of plants for the chemical industry an enormous range of scaffolding parts for assembly of scaffolding units to be used is required.
For the construction work, detailed construction plans are essential, which are nowadays usually provided as three-dimensional (3D) plans. These construction plans, in particular, contain information on all building structures of the projected industrial plant, in particular on buildings, reactors, crackers, cokers, pipes for fluid transfer, electrical installations and so forth.
The total costs for the scaffolding and the scaffolding work provided on site significantly contribute to the total costs in industrial plant construction. Further, from experience, the actual costs incurred in conjunction with the scaffolding during construction of the industrial plant tend to exceed the projected costs by far.
It is, therefore, the object of the invention to provide an improved method for construction of an industrial plant by which scaffolding costs can be further reduced.
The method according to the invention for the construction of an industrial plant, in particular a petroleum refinery, by means of scaffolding units, each of which will be assembled from individual scaffolding components, comprises the following steps:
The drawing of the scaffolding units to be used for the actual construction of the industrial plant together with modifying the construction plan for the use of at least one predetermined scaffolding unit allows for use of a scaffolding unit of a simpler construction as would be necessary otherwise. Thereby, the overall time required for erection and/or dismantling of the predetermined scaffolding unit can be reduced. This offers cost advantages. These effects may actually be multiplied by modifying the construction plan with regard to several building structures for use of a plurality of predetermined scaffolding units. It is understood that the aforementioned scaffolding units may be of the same or of different design. In the latter case, the said scaffolding units may consist of the same or of a different number of scaffolding parts or components, in particular those of identical design.
According to a preferred embodiment of the invention, the 3D construction plan is modified with respect to the spatial arrangement, size and/or construction of the building structure.
With regard to the spatial arrangement of the building structure, the said building structure may e.g. be moved laterally when compared to its original location as depicted in the construction plan. Also, a level adjustment of the building structure may be feasible. Further, the spatial orientation of the building structure with regards to other building structures may be modified to thereby accommodate the predetermined scaffolding unit in the construction plan and on the construction site during the construction work.
By these measures, the predetermined scaffolding unit having e.g. a fixed height, width or length may be integrated and drawn in the construction plan and be used for construction during the actual construction of the industrial plant.
According to a preferred embodiment of the invention, the 3D construction plan is modified with respect to a building structure which is designed as a fluid line or as an electrical line. Fluid lines are an essential component of industrial, in particular chemical, plants and are commonly used for transport of petroleum, water, gases and the like from the site of one production process to another or e.g. to a storage tank. Such industrial fluid lines may have a diameter up to 20 feet and may run several floors above the ground. Repositioning of such a fluid line a few inches or feet may allow use of a much simpler and more cost-efficient predetermined scaffolding unit than without these measures.
According to a further embodiment of the invention, a welding seam of the aforementioned fluid line is repositioned such that it can be generated by use of the predetermined scaffolding unit. In particular for the construction of petroleum refineries or other chemical plants there is such a large number of welding seams for fluid lines is necessary that this measure alone can significantly reduce the overall scaffolding costs for the industrial plant.
According to a further embodiment of the invention, modifying the construction plan is done with respect to a load-bearing building structure of the industrial plant. The load-bearing structure may, in particular, be a foundation, a supporting column of steel and/or concrete or a longitudinal/cross beam.
According to a further embodiment of the invention, the at least one building structure is provided with support points for the predetermined scaffolding unit. Providing the building structure with support points may be accompanied by a modification of the structural dimensioning of the building structure to increase its load-bearing capacity required for support of the predetermined scaffolding unit.
According to the invention, the predetermined scaffolding unit is advantageously designed as a sliding scaffolding unit which may be rail guided. In particular, the aforementioned support points may serve to support the said rails for the rail-guided scaffolding unit.
According to a yet further embodiment of the invention, the provision of the 3D-construction plan and drawing of the scaffolding units in the 3D construction plan including modifying the 3D construction plan is done by means of a computer-installed software. The 3D construction plan is thus provided in an electronic and computer-readable format which may be viewed by means of the software.
According to a preferred embodiment of the invention, the method comprises providing a predefined range of different scaffolding units in the software and selecting at least part of the scaffolding units to be used for the construction of the industrial plant therefrom. By this, the drawing of the individual scaffolding units in the 3D construction plan is facilitated and can be performed much faster.
According to an embodiment of the invention, the scaffolding units to be used for construction of the industrial plant, in particular the ones which are predefined in the software, can all be assembled from scaffolding parts which are compatible with each other and which belong to a manufacturer-specific scaffolding type or system.
For a fuller understanding of the nature and objects of the invention, reference should be made to the following detailed description taken in connection with the accompanying drawings wherein:
Reference is now made to
A first step 102 comprises providing a 3D-construction plan 10 of the industrial plant 12. In step 102, the 3D construction plan 10 is preferably provided in a computer-readable electronic format. Thereby, the 3D construction plan 10 may be conveniently visualized for a user as a whole and in detail by means of a suitable computer (graphics) software 14 which is installed on a computer 16 as shown in
A following step 104 of the method 100 according to the invention comprises drawing of scaffolding units 20, 20′ to be used for the construction of the industrial plant 12 in the 3D construction plan 10 with modifying the 3D construction plan 10 with respect to at least one of the building structures 18 of the industrial plant 12 for use of a predetermined scaffolding unit 20, 20′. The drawing of the scaffolding units 20, 20′ in the 3D construction plan 10 can, in particular, be done by means of the computer-installed software 14 (
In
The 3D construction plan 10 of the industrial plant 12 can, for instance, be modified with respect to a spatial arrangement of the building structure 18. For instance, the fluid line 18b, the column 18c or the wall as shown in
Further, the building structure 18, in particular when structured as a column 18c as shown in
It needs to be understood, that the cost-saving effect of the method 100 according to the invention may be potentiated if the 3D construction plan 10 is modified with respect to several building structures 18 of the industrial plant 12 for use of a plurality of predetermined scaffolding units 20, 20.
According to the invention, method 100 further comprises building step 106 of the industrial plant according to the modified construction plan 10 and by use of the scaffolding units 20, 20′ drawn in the 3D construction plan 10.
The method 100 according to the invention as described above is, overall, based on the underlying concept of making small modifications to one or more building structures 18 of the projected industrial plant 12 to thereby enable the use of (a) predetermined scaffolding unit(s) 20, 20′ which may be of a specified simple construction and/or which may be assembled/disassembled in a more time-efficient manner and/or which offer wider usage options as is the case, for instance, in a rail-guided sliding scaffolding unit when compared to the scaffolding units that would be necessary for the construction work without such modifications.
Lawrence, Dave, Grassa, Giovanni, Skelton, Rod
Patent | Priority | Assignee | Title |
Patent | Priority | Assignee | Title |
8249909, | Oct 31 2008 | Hitachi-GE Nuclear Energy, Ltd. | System and method for visualizing the construction progress of scaffolding utilizing 3D CAD models |
20140257764, | |||
JP2000048061, | |||
JP3524389, | |||
JPT108706, | |||
WO2007113250, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Mar 15 2016 | Peri GmbH | (assignment on the face of the patent) | / | |||
Jul 03 2016 | GRASSA, GIOVANNI | Peri GmbH | CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNEE ADDRESS PREVIOUSLY RECORDED ON REEL 039357 FRAME 0297 ASSIGNOR S HEREBY CONFIRMS THE ASSIGNMENT | 041213 | /0399 | |
Jul 03 2016 | GRASSA, GIOVANNI | Peri GmbH | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 039357 | /0297 |
Date | Maintenance Fee Events |
Jan 11 2023 | M1551: Payment of Maintenance Fee, 4th Year, Large Entity. |
Date | Maintenance Schedule |
Aug 20 2022 | 4 years fee payment window open |
Feb 20 2023 | 6 months grace period start (w surcharge) |
Aug 20 2023 | patent expiry (for year 4) |
Aug 20 2025 | 2 years to revive unintentionally abandoned end. (for year 4) |
Aug 20 2026 | 8 years fee payment window open |
Feb 20 2027 | 6 months grace period start (w surcharge) |
Aug 20 2027 | patent expiry (for year 8) |
Aug 20 2029 | 2 years to revive unintentionally abandoned end. (for year 8) |
Aug 20 2030 | 12 years fee payment window open |
Feb 20 2031 | 6 months grace period start (w surcharge) |
Aug 20 2031 | patent expiry (for year 12) |
Aug 20 2033 | 2 years to revive unintentionally abandoned end. (for year 12) |