A closed operation subsea well tool assembly with a flushing system flushing a first fluid in the main bore (15) of the tool assembly (1). The flushing system of the tool assembly comprises a container (19) with a second fluid, a pump (2), a swab valve (20) in the top of the main bore (15), an inlet (3) in the bottom of the main bore of the tool assembly, which is connected to the pump. Outlet(s) (5a, 6a) are below the swab valve, configured to guide out the first fluid from the main bore. A fluid channel (7) extends from the outlet (5a, 6a) and down to channels of the wellhead module (10) or the wellhead (31). Methods using the tool assembly are also disclosed.
|
1. A closed operation subsea well tool assembly for use in performing closed operations on a subsea well or on a wellhead module or a wellhead which is installed on the subsea well, the tool assembly being connectable to the wellhead module or the wellhead and comprising:
a main bore which extends axially through the tool assembly;
a flushing system which is configured to flush a first fluid from the main bore, the flushing system comprising:
a container which contains a second fluid;
a pump which is connected to the container;
at least one of an end cap and a first valve which is located at a top of the main bore, the first valve being configured to provide full mechanical access to the main bore in an open position;
an inlet which is connected to a bottom of the main bore, the pump being connected to the inlet;
at least one outlet which is connected to the top of the main bore below the at least one of the end cap and the first valve; and
a fluid channel having a first end which is connected to the at least one outlet and a second end which is connectable to a channel which is located in the wellhead module or in the wellhead;
wherein in operation of the flushing system, the pump is activated to pump the second fluid through the inlet and into the main bore to thereby displace the first fluid through the outlet and the fluid channel and into the channel located in the wellhead module or in the wellhead.
2. The tool assembly according to
4. The tool assembly according to
7. The tool assembly according to
8. The tool assembly according to
9. A method of using the tool assembly of
with the tool assembly, lowering a wellhead module on a wire from a drilling rig or a ship;
landing the wellhead module on the wellhead;
using the tool assembly, pulling or opening a pre-installed barrier element in the top of the wellhead to thereby enable well fluid to rise up into the main bore;
using the tool assembly, closing and testing valves of the wellhead module;
using the tool assembly, flushing the well fluid from the main bore;
disconnecting the tool assembly from the wellhead module and retrieving the tool assembly to the drilling rig or ship.
10. A method of using the tool assembly of
installing the tool on a wire from a drilling rig or a ship;
landing the tool assembly on the wellhead module;
setting a barrier element in the wellhead and pressure testing the barrier element using the pump and a fluid from the container;
closing the valves of the main bore of the wellhead module;
flushing well fluid from the main bore;
disconnecting the wellhead module from the wellhead and retrieving the wellhead module to the drilling rig or ship on the wire.
|
The invention relates to a fluid circulation system for use in a tool that makes mechanical and/or pump operations possible in subsea wells or wellheads, without the use of wire or coiled tubing up to the rig, ship or platform. In particular, the present invention relates to flushing of an enclosed cavity which may contain a well tool arranged in a well liquid environment, without the well barriers for well control being penetrated or containing fluid inflow to the operation vessel, so that flushing is performed without exposure or return of hydrocarbons to the vessel. It is also vital that the invention avoids high pressure well liquid, such as hydrocarbons, back to the operation vessel, so that a more plain ship can be used for the desired well operation.
The background of the invention is the need in the petroleum industry for cost reducing subsea operation with an equal or higher level of safety, compared to the present practice. It is commonly known that developing and operating a subsea field that typically has multiple wells with associated Xmas trees requires a large investment both in equipment and operational costs. A large portion of the cost for such a development stems from the drilling, completion, startup and service of the wells. Traditionally the industry has used large drilling rigs with appurtenant drilling system for drilling towards a reservoir, and then installing a subsea wellhead and well casings. When these have been installed, an Xmas tree (well head module) is landed on the wellhead in order to control the production after starting up. It has been common to also install the Xmas tree from the drilling rig. Starting up the well is typically performed with so-called workover systems (service systems) which are connected to the Xmas tree and which provide a mechanical access from the drilling rig to the subsea well and reservoir. It will be possible to run an internal work tool on a steel wire (wireline operation) or a small work pipe (coiled tubing—typically a 2″ pipe) down into the well, by means of a workover system, in order to pull plugs and to open to reservoirs for production. Such a workover system can also be used for service in the well and for control or optimization of the production throughout the lifetime of the well. Common for such operations and systems is that they involve large costs to manufacture, operate and maintain.
Accordingly there exists a demand for solutions that are useful for installation and testing of subsea Xmas trees, as well as well service, without the use of a drilling rig. This technology or equipment shall therefore make it possible to move such operations to lighter vessels or ships which are not necessarily required to handle hydrocarbons up to the vessel deck. It will also be advantageous to let the drilling rig perform the operation for which it is optimized, namely to drill the well and to install casings and tubing. This will result in a more efficient use of the drilling rig, since it then does not need to shift between the types of risers which are in use. The logistic aboard the rig will also become easier if the Xmas tree is not taken aboard, since this requires both space and handling of large weights (typically 30-50 tons). The heavy weight and the size of a workover system is also significant, as such a system includes many containers on deck, as well as large reels with umbilicals.
It will be desirable to introduce new technology which reduces the operational costs, has less weight and size, and does not expose personnel to equipment exposed to well pressure. This will provide reduced requirements to the lifting and handling equipment on the vessel, as well as improved HSE. A main reason for the large weight of drilling and workover systems is the requirement of cutting the drilling or work string that penetrates the barrier envelopes if needed. An example of this will be at loss of well control, where the main safety valves must be activated to shut in or isolate the well from the environment. Such safety valves are typically known as elements in a blowout preventer (BOP) or a lower riser package (LRP). The weight of a BOP can typically be from 200 tons to 500 tons, while an LRP typically has a weight of 30 tons to 50 tons. An object of the present invention is to flush a main bore in an installation and intervention tool where the barrier envelopes are not penetrated, so that the requirement of cutting functionality can be avoided. This will again result in significantly lighter equipment for maintaining well control. Another desirable object is to avoid well exposure directly up to the vessel. This also includes avoiding potential direct or indirect leakage paths through attached hoses and pipes (umbilicals). It is essential that the tool does not contain pressurized hydrocarbons when it is placed on the vessel, before or after the well operation, so that less requirements are raised for such handling aboard.
Alternative systems for flushing have been suggested, and the nearest known art is described in the patent publications NO330819, NO309439, WO2011/039514, and US2011/0192610. Common for these solutions is that they will potentially expose the operation vessel to hydrocarbons—either directly by carrying along filled tanks or indirectly via leakages through attached umbilicals or pipes. Their use also requires that the suggested systems operate together with a well control package (lower riser package/well control package), as the known art discusses use in association with a subsea lubricator where a tool string (wire) penetrates through a pressure control head (pack box and grease injector head). This implies the inclusion of a closing and cutting valve on the lower side of the pressure control head as a result of the penetration.
The object of the invention is to make a closed well operation possible. With closed well operation is meant activities down in a subsea well without the use of cable or coiled tubing that penetrates well barriers, or use of riser from well to vessel.
According to a first aspect of the present invention, a tool assembly is provided which is a closed operation subsea well tool assembly. The tool assembly has a flushing system configured for flushing of a first fluid in the main bore of the tool assembly. The flushing system of the tool assembly comprises a container that contains a second fluid and a pump that is connected to the container. The tool assembly also comprises an upper swab valve in the top of the tool assembly with full mechanical access to the main bore in the open position, or an end cap. Further, the tool assembly comprises an inlet in the bottom of the main bore of the tool assembly, which is connected to the pump, one or more outlets below the swab valve in the top of the main bore of the tool assembly, which are configured to release the first fluid from the main bore of the tool assembly, and a fluid channel that extends from the outlet and down to channels of the wellhead module or the wellhead.
The closed operation subsea well tool assembly according to the invention is for closed operation of subsea wells or associated well modules.
With the use of term closed operation is meant that the tool assembly is employed without penetration of well barriers and associated cutting functions. That is, the operation is performed without crossing any well barriers.
The tool assembly can advantageously be operated on a wire from a surface vessel.
In an embodiment of the tool assembly, the second fluid contained in the container is a hydrate inhibiting agent, and/or the container is pressure-compensated with respect to the environment.
The pump can in some embodiments be supplied with power and operated from an ROV or a separate electric umbilical from the operation vessel.
Advantageously, the inlet in the bottom of the main bore of the tool assembly is supplied with one or more isolation valves, check valves or a combination of such.
Also, the outlet or the outlets in the top of the main bore of the tool assembly can be provided with one or more isolation valves, check valves or a combination of such.
The fluid channel from the outlet and down to the channels of the wellhead module can in some embodiments be significantly smaller than the main bore of the tool assembly, so that the velocity of the flowing liquid is higher than the rising rate of gas bubbles.
The fluid channel from the outlet can advantageously be provided with one or more isolation valves, check valves or a combination of such.
The pump, with fluid supply from the container with the second fluid, can in some embodiments be configured for pressure testing of well barrier elements within the tool assembly, wellhead module or the wellhead.
According to a second aspect of the present invention, a method is provided for using the tool assembly when installing a wellhead module, such as a Xmas tree. The method comprises the following steps:
According to a third aspect of the present invention, a method is provided for using the tool assembly when pulling a wellhead module, such as a Xmas tree. The method is characterized by the following steps:
A well control package which comprises cutting and sealing elements in its main bores will thus be excessive, since the pressurized hydrocarbons of the well already are enclosed and isolated from the environment with the tool, wellhead module, and possible deeper deployed plugs/valves in the well. The starting point after an ended drilling operation will always be a well which is isolated with two barrier envelopes that means that the reservoir must overcome at least two sealing elements in all directions towards the environment. This is normally referred to as the primary and secondary barrier, where the primary barrier is all the closest sealing elements towards well pressure, while the secondary barrier is an envelope of all the next external sealing elements. It is further divided between vertical and horizontal completion of the well, for start of production. Vertical completion will involve a vertical Xmas tree (VXT) where the production tubing is hung off in the wellhead before installation of the VXT. Horizontal completion will on the other hand involve a horizontal Xmas tree (HXT), where the production tubing is hung off in the HXT itself. This results in that the HXT must be installed on the wellhead before the tubing is run. Both types of completion will involve operation and systematic movement of controlled barrier elements in such a way that the well and the reservoir can start production without releasing hydrocarbons to the environment. This applies to the entire life of a well, from drilling operations, completion and production start, to production, service (intervention) and finally permanent shutdown (so-called plug and abandonment—P & A).
As described above, a vertical completion with a VXT will result in that the well is isolated with two barriers before the VXT itself is installed. This can for instance be performed with mechanical plugs or valves within the tubing. The said tool can for instance be used for installation of a VXT with a following operation or pulling of a plug which is arranged high up in the tubing. It will not be unexpected that there may exist pressurized well fluid (hydrocarbons) below the plug, so that this may come up through the VXT and further up in the main bore of the tool. A disconnection of the tool from the wellhead module can hence result in that this fluid (gas or liquid) will be released to the environment, unless this is removed before disconnection.
While various features of the present invention have been discussed above in general terms, a more detailed and non-limiting example of an embodiment will be provided in the following description, with reference to the drawings, in which:
The tool as shown in
The said pump (2) can, in addition to its primary function of flushing the main bore, be used for pressure testing of desired barrier elements such as valves and seals in the tool, the wellhead module, the wellhead, well or any connected units. The figure shows a line (12) for pressure testing of the seal element between adapter (11) and wellhead module (10), but the pressure can also come via the inlet (3) to the main bore.
The invention, as placed into a larger system as shown in
For alternative operations, a rig (43) can be used with a riser (38) and a traditional workover system (37).
Operational Method:
A method for closed well operation with the tool (1) of the present invention is shown in
Carlsen, Tor-Øystein, Løkka, Trond
Patent | Priority | Assignee | Title |
Patent | Priority | Assignee | Title |
4993492, | Nov 13 1984 | The British Petroleum Company, p.l.c. | Method of inserting wireline equipment into a subsea well |
6200068, | Feb 06 1998 | SAIPEM AMERICA INC | Hot tap fluid blaster apparatus and method of using same |
7165619, | Mar 07 2002 | VARCO I P, INC | Subsea intervention system, method and components thereof |
7331393, | Oct 01 1999 | FMC KONGSBERG SUBSEA AS | Subsea lubricator device and methods of circulating fluids in a subsea lubricator |
20100032163, | |||
20110011593, | |||
20110192610, | |||
20120241161, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Apr 08 2016 | FMC KONGSBERG SUBSEA AS | (assignment on the face of the patent) | / | |||
Oct 30 2017 | CARLSEN, TOR-ØYSTEIN | FMC KONGSBERG SUBSEA AS | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 045043 | /0534 | |
Dec 05 2017 | LØKKA, TROND | FMC KONGSBERG SUBSEA AS | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 045043 | /0534 |
Date | Maintenance Fee Events |
Oct 08 2017 | BIG: Entity status set to Undiscounted (note the period is included in the code). |
Feb 08 2023 | M1551: Payment of Maintenance Fee, 4th Year, Large Entity. |
Date | Maintenance Schedule |
Aug 20 2022 | 4 years fee payment window open |
Feb 20 2023 | 6 months grace period start (w surcharge) |
Aug 20 2023 | patent expiry (for year 4) |
Aug 20 2025 | 2 years to revive unintentionally abandoned end. (for year 4) |
Aug 20 2026 | 8 years fee payment window open |
Feb 20 2027 | 6 months grace period start (w surcharge) |
Aug 20 2027 | patent expiry (for year 8) |
Aug 20 2029 | 2 years to revive unintentionally abandoned end. (for year 8) |
Aug 20 2030 | 12 years fee payment window open |
Feb 20 2031 | 6 months grace period start (w surcharge) |
Aug 20 2031 | patent expiry (for year 12) |
Aug 20 2033 | 2 years to revive unintentionally abandoned end. (for year 12) |