A process and device for charging a plurality of tubes in a tube reactor with granular solids, preferably with catalysts, which, for this purpose, are fed from one or more stock vessels to a controllable metering device and from there, via guiding and directing devices and flexible hose connections, successively into the tubes to be filled, wherein, during the packing of the tubes, a stream of gas of constant amount is generated, which can, after an individual tube has been packed, be passed temporarily, via one or more controllable valves, through this packed tube, a pressure drop measurement being carried out at the same time and the differential between the measured value and the predetermined intended value being used to determine a small additional amount of packing material which is subsequently introduced into the tube which has been subjected to measurement, and wherein thereafter a program control triggers the mechanical packing of the next tube, metered in the same manner, with subsequent pressure drop measurement and metering of the additional amount.

Patent
   4461327
Priority
Jun 02 1980
Filed
May 28 1981
Issued
Jul 24 1984
Expiry
Jul 24 2001
Assg.orig
Entity
Large
23
6
all paid
1. A process for charging a plurality of tubes in a tube reactor with granular catalysts, which, for this purpose, are fed from at least one stock vessel to a controllable metering device and from there, via guiding and directing devices and flexible hose connections, successively into the tubes to be filled, wherein, during the packing of the tubes (2), a stream of gas of constant amount is generated, which can, after an individual tube has been packed, be passed temporarily, via one or more controllable valves, through this packed tube, a pressure drop measurement being carried out at the same time and the differential between the measured value and the predetermined intended value being used to determine a small additional amount of packing material which is subsequently introduced into the tube which has been subjected to measurement, and wherein thereafter a program control triggers the mechanical packing of the next tube, metered in the same manner, with subsequent pressure drop measurement and metering of the additional amount.
2. The process of claim 1, wherein a metering belt-weigher with a short settling time and a wide adjustment range is used as the gravimetric metering device for the principal amount and residual amount of the packing to be introduced successively into the tubes.
3. The process of claim 1, wherein the constant-amount stream of gas which is temporarily to be passed through individual pre-packed tubes is introduced, as a stream under pressure, via a nozzle (4) which opens into the discharge line of a guiding and directing device (9) for the packing material and possesses a controllable valve (V2), in such a way that on opening this valve (V2) a further valve (V1) in the discharge line is closed simultaneously, the pressure measurement (PIS) taking place above the packing in the particular tube.
4. The process of claim 1, wherein the constant-amount stream of gas, to be passed temporarily through successive prepacked tubes (2) is generated as a suction stream and one or more valves (V3), to be opened temporarily for carrying out the suction measurement, are located at the lower end of the tubes (2).
5. The process of claim 4, wherein a filter (8) for abraded dust from the packing is located in the line (5a) which connects a suction pump (7), via the valves (V3), with the lower ends of the tubes (2).
6. The process of claim 3 or 4 or 5, wherein pressure-measuring instruments (PIS) with switch contacts are used, by means of which contacts the adjustment range of the metering device (3) is automatically variable to suit the remaining amount of packing to be introduced by precision metering.

The present invention relates to a process for mechanically charging a plurality of tubes in tube reactors with granular solids, preferably with catalysts, which process employs a controllable metering device and in particular employs the interpolation of programable pressure-drop measurements on all tubes individually in succession, after the principal amount has been introduced, and a control adjustment, resulting from each individual measurement, of the metering device, in order to introduce the correct residual amount, and to arrangements for carrying out this process.

German Patent Application No. P 2,849,664 describes a process by means of which granular solids, preferably catalysts, are introduced into the reactor tubes by means of continuously conveying and controllable metering devices, for example metering-type belt weighers, via a conduit; the process can be carried out not only with homogeneous solids but also, in a program-controlled manner, with mixed solids of different character.

In spite of the high reproducibility of this mechanical filling and metering process, substantial variations in the pressure drop in individual packed tubes are encountered when packing large industrial reactors. This is essentially attributable to two causes: to pack large industrial tube reactors, the amount of catalyst required is about 50 tonnes or more. In the production of such large amounts of catalyst, slight differences in physical properties, for example in bulk density, surface roughness, resistance to breaking etc., necessarily arise. In an industrial tube reactor with, for example, up to 40,000 individual tubes, it is furthermore virtually impossible to use tubes which all have exactly the same internal diameter. For example, in tube reactors for the acrylic acid process, the tube dimension tolerance is ±1.5%, and according to DIN specifications even ±2.5% is permissible.

Since substantial differences in the pressure drop in the individual tubes must, for technological reasons, not occur, two additional process steps have hitherto been necessary after complete packing of the reactor, namely pressure difference measurements on the individual tubes, and an equalization of the pressure, with the aim of setting up identical pressure drops for all the tubes. These process steps require personnel, and expenditure of time, to an extent comparable with the actual filling process, ie., for example, about 700 man hours per reactor.

It is an object of the present invention to supplement the mechanical process for the accelerated packing of tube reactors, disclosed in the application referred to above, with mechanical means for pressure drop equalization during the actual packing process, so that an additional pressure balancing after complete packing of the reactor becomes unnecessary.

According to the invention, this object is achieved by a process wherein, during the packing of the tubes, a stream of gas of constant amount is generated, which can, after an individual tube has been packed, be passed temporarily, via one or more controllable valves, through this packed tube, a pressure drop measurement being carried out at the same time and the differential between the measured value and the predetermined intended value being used to determine a small additional amount of packing material which is subsequently introduced into the tube which has been subjected to measurement, and wherein thereafter a program control triggers the mechanical packing of the next tube, metered in the same manner, with subsequent pressure drop measurement and metering of the additional amount.

The process according to the invention is based on the gravimetric metering--disclosed in the publication referred to at the outset--of the solid to be packed into the tubes. The requirement that this solid should be a homogeneous packing instead of a variable mixed packing can be met by carrying out the packing process continuously and in particular introducing the packing material at a constant mass flow rate into the tubes via the gravimetrically operating metering device. A particularly suitable metering device is a metering belt-weigher or a comparable gravimetrically conveying metering system with a wide adjustment range for the mass flow which is to be varied.

Two different arrangements can be used to carry out the process.

Arrangement 1, as shown in FIG. 1 of the drawings, is employed if, for packing the reactor tube bundle, only the top of the reactor is accessible. In the arrangement 2 shown in FIG. 2, the reactor must be accessible both from the top and from the bottom. In certain cases, arrangement 2 can offer advantages because fine abraded dust from the solid to be packed into the reactor can be removed in a filter.

The entire equipment is shown diagrammatically in FIG. 1. The packing takes place as follows:

1. Main metering

The reactor tube (2) is packed, at a constant mass flow rate m1 of the packing, provided by the metering belt-weigher 3, for a predetermined time T1.

m1 and T1 are selected so that the amount packed into the tube, namely M1 =m1 ·T1 is somewhat less than the total packing M. ##EQU1## where T=total packing time per tube and M=total amount of packing per tube. M1 should be only slightly less than M and is advantageously established experimentally.

2. At the end of the packing time T1 of each individual tube 2, the valve V1 is closed and the valve V2 is opened briefly. A stream of gas, which is kept constant by means of a flow regulator, then passes through the amount M1, packed into the tube, via the nozzle 4. The lower orifice of the tube 2 being packed is directly connected to the atmosphere. The pressure set up above the packing introduced into the tube 2, namely the effective pressure pe, corresponds to the pressure drop caused by the packing M1. The measured value p1 is compared with a predetermined intended value p which corresponds to the amount M, and the amount of packing M-M1 which still requires to be metered in is calculated. The relationship between p-p1 and M-M1 is approximately linear.

3. The shortfall amount M-M1 is metered in. To do this, the program control, which influences the timing of the entire arrangement, is used to vary the speed of the metering belt-weigher 3, ie. the weigher is employed for precision metering. For this purpose, it is particularly advantageous if the metering belt-weigher employed has a particularly large adjustment range and settles very quickly, rather than resorting to the alternative of having a rough metering device and precision metering device. For rough metering and precision metering, the metering belt-weigher is actuated in the form of a start-stop operation, for which a program control of a conventional type is produced.

4. After completion of process 3, ie. at the end of time T, a controlled pressure measurement above the packing in tube 2 is carried out, corresponding to the conditions described above in section 2. If the measured value deviates from the intended value p by more than a certain tolerance, a signal is generated as part of the program control.

In order to be able to measure the pressure drop occurring at the packing in any particular tube 2 as accurately as possible, a gas-tight seal is needed between the upper end of the reactor tube and the filling nozzle of the flexible fabric hose 5, by means of which the discharge line below the valve V1 is successively connected to the tubes 2 which are to be filled. In the simplest case, this is achieved by manually pressing down the filling nozzle, a soft gasket being interposed. The process can be automated by providing an electromagnet 6 which annularly surrounds the conical filling nozzle and which, for the duration of the pressure measurement, presses this nozzle onto the end of the reactor tube 2. This electromagnet 6 is actuated by the program control.

The filling and metering system for the reactor tubes 2, which consists of the controllable metering belt-weigher 3 and flexible fabric hoses 5 leading to the reactor tubes, is the same as in arrangement I. In the present case, however, the device which generates the constant stream of gas, preferably a flow-controlled suction pump 7, is connected to the underside of the reactor. The sealing of the flexible hoses 5a against the lower ends of the tubes 2 is effected as in arrangement I. Each tube 2 is charged with the solid until a predetermined pressure drop over the packing is reached at the tube. It is advantageous if the pressure-measuring device PIS is provided with two or more switch contacts, using which successive principal metering and precision metering by means of the metering belt-weigher 3 can be effected. This achieves greater accuracy of metering and the hold-up in the metering system, which, as an overrun, enters the particular tube 2 as additional packing can be kept very small.

In order to keep the entire system substantially free of fine abraded dust from the solid being packed into the tubes, it is advisable to lead the stream of gas from the top of the reactor to the underside of the reactor, ie. to install a vacuum generator 7 with flow regulator on the underside of the reactor. A dust separator 8 can then be installed on this suction side of the vacuum system (FIG. 2).

With both arrangements (I and II) it is possible, by means of a guiding and directing device 9, which comprises a shunt 9a, to have a plurality of filling systems underneath the metering belt-weigher 3. FIG. 2 shows such a twin arrangement diagrammatically. In such a case, the shunt 9a must be linked into the central program control.

Engert, Gerd-Juergen, Magin, Rudolf, Nenninger, Franz

Patent Priority Assignee Title
4653322, Jul 05 1985 Westinghouse Electric Corp. Remote level measurement in a solid-liquid system
5906229, Apr 26 1996 TOTAL RAFFINAGE DISTRIBUTION S A Method and device for the uniform filling of particles of a solid catalyst into a tubular reactor
6725706, Mar 16 2001 Tubemaster, Inc Device and method for blowing down and measuring the back pressure of chemical reactor tubes
6981404, Mar 16 2001 Tubemaster, Inc Device and method for use with chemical reactor tubes
6981529, Jun 28 2002 QUANTA ASSOCIATES, L P Measuring catalyst(s) for filling reactor tubes in reactor vessels
7309201, Dec 21 2005 QUANTA ASSOCIATES, L P Providing automated delivery of catalyst and/or particulate to any filling system device used to fill tubes
7439455, Jun 28 2002 QUANTA ASSOCIATES, L P Measuring catalyst(s) for filling reactor tubes in reactor vessels
7528281, Dec 28 2001 MITSUBISHI RAYON CO , LTD ; Mitsubishi Chemical Corporation Method for vapor phase catalytic oxidation
7667072, Dec 28 2001 MITSUBISHI RAYON CO , LTD ; Mitsubishi Chemical Corporation Method for vapor phase catalytic oxidation
7673496, Mar 16 2001 Tubemaster, Inc Device for measuring back pressure in chemical reactor tubes
7748255, Mar 16 2001 Tubemaster, Inc Method for assessing chemical reactor tubes
7776288, Mar 23 2006 SUD-CHEMIE IP GMBH & CO KG Charging device for a tubular reactor
7818995, Mar 16 2001 Tubemaster, Inc Device for measuring back pressure in open-ended chemical reactor tubes
7850928, Jan 25 2001 Nippon Shokubai Co., Ltd. Fixed-bed shell-and-tube reactor and its usage
7897120, Mar 24 2005 SUD-CHEMIE IP GMBH & CO KG Feeding device for bundled tube reactor
7913543, Mar 16 2001 Tubemaster, Inc Method of using a device for measuring the back pressure in chemical reactor tubes
7927555, Mar 08 2005 BASF Aktiengesellschaft Charging of a reactor
7984654, May 31 2006 SUD-CHEMIE IP GMBH & CO KG Testing device for tube bundle reactors
8011393, Aug 13 2007 Unidense Technology GmbH Process and device for filling a tube with granular material
8550127, Aug 13 2008 Unidense Technology GmbH Catalyst loading system
8578978, Oct 01 2009 IFP Energies Nouvelles Device for loading particles of catalyst into tubes having an annular zone
8753452, Mar 16 2001 Tubemaster, Inc Method for treating vertical tubes in a chemical reactor
9289740, Aug 13 2007 Unidense Technology GmbH Catalyst loading system
Patent Priority Assignee Title
3627555,
3788368,
3968904, Mar 12 1974 AMF Incorporated Continuous measurement of the bulk density of particulate material
4163464, Feb 11 1977 Rheinische Braunkohlenwerke AG Arrangement for filling a vessel which is to be put under high pressure, with freely flowing solids
4191223, Apr 18 1978 Powder transfer system
DE2849664,
////
Executed onAssignorAssigneeConveyanceFrameReelDoc
May 13 1981MAGIN, RUDOLFBASF AktiengesellschaftASSIGNMENT OF ASSIGNORS INTEREST 0041950342 pdf
May 13 1981NENNINGER, FRANZBASF AktiengesellschaftASSIGNMENT OF ASSIGNORS INTEREST 0041950342 pdf
May 13 1981ENGERT, GERD-JUERGENBASF AktiengesellschaftASSIGNMENT OF ASSIGNORS INTEREST 0041950342 pdf
May 28 1981BASF Aktiengesellschaft(assignment on the face of the patent)
Date Maintenance Fee Events
Nov 25 1985ASPN: Payor Number Assigned.
Dec 30 1987M170: Payment of Maintenance Fee, 4th Year, PL 96-517.
Jan 24 1992M184: Payment of Maintenance Fee, 8th Year, Large Entity.
Dec 27 1995M185: Payment of Maintenance Fee, 12th Year, Large Entity.


Date Maintenance Schedule
Jul 24 19874 years fee payment window open
Jan 24 19886 months grace period start (w surcharge)
Jul 24 1988patent expiry (for year 4)
Jul 24 19902 years to revive unintentionally abandoned end. (for year 4)
Jul 24 19918 years fee payment window open
Jan 24 19926 months grace period start (w surcharge)
Jul 24 1992patent expiry (for year 8)
Jul 24 19942 years to revive unintentionally abandoned end. (for year 8)
Jul 24 199512 years fee payment window open
Jan 24 19966 months grace period start (w surcharge)
Jul 24 1996patent expiry (for year 12)
Jul 24 19982 years to revive unintentionally abandoned end. (for year 12)