A method for efficiently producing, transporting, offloading, storing and distributing a natural gas to a marketplace. The method comprising producing the natural gas from a first subterranean formation, liquefying the natural gas to produce a liquefied natural gas, transporting the liquefied natural gas to a re-gasification platform, offloading and pressurizing the liquefied natural gas, re-gasifying the liquefied natural gas to produce a re-gasified natural gas, and injecting the re-gasified natural gas into a second subterranean formation which is capable of storing natural gas and producing a product natural gas stream therefrom and transporting the product natural gas stream via a distribution system to a marketplace.
|
16. A method for efficiently distributing to a marketplace a liquefied natural gas, the method comprising:
a) re-gasifying the liquefied natural gas to produce a re-gasified natural gas; and, b) injecting the re-gasified natural gas into a subterranean formation which is capable of storing the re-gasified natural gas and producing a product natural gas stream therefrom and transporting the produced natural gas stream via a distribution system to a marketplace.
1. A method for efficiently producing, transporting, storing and distributing to a marketplace a natural gas, the method comprising:
a) producing the natural gas from a first subterranean formation; b) liquefying the natural gas to produce a liquefied natural gas; c) transporting the liquefied natural gas to a re-gasification platform; d) re-gasifying the liquefied natural gas to produce a re-gasified natural gas; and e) injecting the re-gasified natural gas into a second subterranean formation which is capable of storing natural gas and producing a product natural gas stream therefrom and transporting the product natural gas stream via a distribution system to a marketplace.
15. A method for efficiently producing, transporting, offloading, storing and distributing to a marketplace a natural gas, the method comprising:
a) producing the natural gas from a first subterranean formation; b) liquefying the natural gas to produce a liquefied natural gas; c) transporting the liquefied natural gas to a re-gasification facility; d) offloading and pressurizing the liquefied natural gas; e) re-gasifying the liquefied natural gas to produce a re-gasified natural gas at boosted pressure; and f) injecting the re-gasified natural gas into a second subterranean formation which is capable of storing natural gas and producing a product natural gas stream therefrom and transporting the product natural gas stream via a distribution system to a marketplace.
2. The method of
3. The method of
4. The method of
5. The method of
6. The method of
7. The method of
8. The method of
9. The method of
10. The method of
11. The method of
12. The method of
13. The method of
14. The method of
17. The method of
18. The method of
19. The method of
20. The method of
|
1. Field of the Invention
This invention relates to an efficient method for producing, transporting, offloading, pressurizing, storing and distributing to a marketplace a natural gas which is produced from a subterranean formation remotely located relative to the marketplace utilizing a subterranean formation capable of storing natural gas.
2. Brief Description of the Prior Art
Because of its clean burning qualities and convenience, natural gas has been widely used in recent years both for industrial use and for home heating. Many sources of natural gas are located in remote areas, which are not conveniently available to any commercial markets for the natural gas. When pipelines are unavailable for the transportation of the natural gas to a commercial market, the produced natural gas is often processed into liquefied natural gas (LNG) for transport to market. One of the distinguishing features of a LNG plant is the large capital investment required for the plant.
A further large investment is required at the destination for the LNG for cryogenic storage tanks near the marketplace to store the LNG until it is marketed. Such cryogenic facilities are relatively expensive and require re-gasification of the LNG for distribution via a pipeline system or the like to the ultimate consumers.
Where pipelines have been available to deliver natural gas to a marketplace, the demand for natural gas has fluctuated widely between low demand periods and peak demand periods. In such instances, natural gas has, in some instances, been stored in subterranean formations or cavities. The natural gas is delivered as a gas to the subterranean storage and subsequently retrieved from the subterranean storage for delivery to a pipeline or other system to distribute it to the ultimate consumers. These systems require that natural gas be available as a gas from pipelines for storage in the subterranean storage areas.
Natural gas is typically available at pressures from about 250 psig (pounds per square inch gauge) to about 10,000 psig at temperatures from 80 to about 350° F. from many subterranean gas-bearing formations. This gas is readily processed by well-known technology into liquefied natural gas. Various refrigeration cycles have been used to liquefy natural gas with the three most common being the cascade cycle which uses multiple single component refrigerants and heat exchangers arranged progressively to reduce the temperature of the gas to liquefaction temperature, the expander cycle which expands gas from a high pressure to a low pressure with a corresponding reduction in temperature, and multi-component refrigeration cycles which use a multi-component refrigerant and specially designed heat exchangers to liquefy the natural gas. Combinations of these processes have also been used. LNG is typically transported by sea in cryogenic tanker ships.
As noted previously, both of these methods entail certain disadvantages, i.e. the transportation of natural gas by pipeline is limited by the availability of the pipeline system; therefore, the storage of natural gas in gaseous form in subterranean formations, cavities or surface storage facilities is limited to those areas in which greater quantities of natural gas can be delivered, then can be used during low demand periods. Similarly, the use of liquefied natural gas, which is liquefied at or near the marketplace, is also limited to those areas where an excessive amount of natural gas can be delivered during at least a portion of the year. As indicated previously, this practice also requires the construction and use of cryogenic tanks, which are relatively expensive.
The use of liquefied natural gas which has been liquefied at a production site at a remote location also requires the use of cryogenic storage space and re-gasification equipment at or near the marketplace so that the LNG can be stored until it is desired to re-gasify the LNG and use it.
As noted above, various systems for producing liquefied natural gas from natural gas are well known. Some such systems are shown, for instance, in U.S. Pat. No. 4,033,735, issued Jul. 5, 1977 to Leonard K. Swenson, and U.S. Pat. No. 5,657,643, issued Aug. 19, 1997 to Brian C. Price, and U.S. Pat. No. 3,855,810, issued Dec. 24, 1974 to Simon et al.
Re-gasification systems for re-gasifying liquefied natural gas are also known. These systems can vary widely but include systems such as open rack vaporizers which are typically used with seawater as a heat exchange medium, shell and tube vaporizers which use either seawater, glycol-freshwater mixtures, or propane and an intermediate as the heat exchange medium. Submerged combustion vaporizers, steam-heated vaporizers and ambient air heated vaporizers are other means for re-gasifying liquefied natural gas. A wide variety of vaporizers can be used so long as they are effective to re-gasify the LNG by heat exchange with some suitable heat exchange medium.
Accordingly, in view of the expense of delivering the natural gas to consumers by either of the foregoing methods, continued efforts have been directed to the development of more efficient methods for delivering natural gas from a remote production site to a marketplace more efficiently.
According to the present invention, a method is provided for efficiently producing, transporting, storing and distributing to a marketplace a natural gas, the method comprises producing the natural gas from a first subterranean formation, liquefying the natural gas to produce a liquefied natural gas, transporting the liquefied natural gas to a re-gasification facility (onshore, offshore or a combination of both), offloading and re-gasifying the liquefied natural gas to produce a re-gasified natural gas at a suitable pressure for injection, and injecting the re-gasified natural gas into a second subterranean formation which is capable of storing natural gas. Production wells and associated facilities with a pipeline to the marketplace are utilized to deliver the stored natural gas to the marketplace from the second subterranean formation.
The FIGURE is a schematic diagram of an embodiment of the present invention.
According to the present invention, a natural gas is efficiently delivered to a marketplace by liquefying the natural gas at or near the production site, transporting the liquefied natural gas to a re-gasification facility, offloading and pressurizing the liquefied natural gas to re-injection pressures, regasifying at pressure and injecting the natural gas into a subterranean formation suitable for storing natural gas as a product for delivery to a marketplace accessible by a distribution system from the second subterranean formation. The re-injection pressure of the gas can be achieved as described above by pressurizing the liquefied natural gas prior to the re-gasification, or by conventional compression equipment for the natural gas after re-gasification, or a combination of both. The re-injection rate of the re-gasified natural gas is equal to the offloading rate of liquefied natural gas thereby eliminating the need for cryogenic liquefied natural gas storage tank facilities at the re-gasification platform. The natural gas is then contained in the second subterranean formation until it is desired to produce the gas for distribution. Production wells and associated facilities with pipeline to the marketplace are utilized to deliver the stored natural gas to the marketplace from the second subterranean formation. The gas may be produced by the same production system previously used to natural gas from the second formation and may be distributed via the same distribution system previously used for the distribution of natural gas from the second subterranean formation.
While natural gas could be delivered as LNG, re-gasified and distributed directly to the pipeline, such requires the construction of expensive cryogenic facilities to store the LNG prior to re-gasification at a relatively continuous rate for a steady supply to the pipeline. Utilizing the second subterranean formation to store the natural gas thereby eliminating the need for cryogenic storage and allowing for variable natural gas production rates to meet market needs. This results in a more economical and flexible system for storing and distributing the LNG than the relatively expensive cryogenic facilities previously used.
As shown in FIG. 1 schematically, an embodiment of the present invention comprises an offshore platform 10 including producing wells and production facilities positioned to produce natural gas from a first remotely located subterranean formation 11, which is a natural gas-producing field. The platform is supported by supports 12 from a sea floor 14 above a sea level 16. The production is achieved via a well 18 as shown by arrow 20. The produced gas is passed via a pipeline 22, which is shown as a pipeline extending from offshore platform 10 to an LNG plant shown schematically at 24. Producing wells and production facilities for the LNG plant may be located offshore as shown or located onshore depending upon the location of the producing subterranean formation 11. LNG plant 24 as shown is positioned on land 26. LNG plant 24 may be positioned on either a platform, floating or grounded vessel, or land, as convenient. In LNG plant 24 the natural gas is liquefied and passed to LNG storage 28. From LNG storage 28, a ship 30, which is shown schematically as an LNG tanker, is loaded and transports the natural gas to a docking and re-gasification platform 32. Platform 32 is supported from sea floor 14 by supports 34. Platform 32 is constructed to be sufficiently sturdy to permit docking and unloading operations from LNG tanker 30. From platform 32 the LNG is pressurized using cryogenic booster pumps and then re-gasified as known to those skilled in the art. The LNG may be re-gasified by the use of any suitable heat exchange system such as an open rack vaporizers, a shell and tube vaporizers using either seawater, glycol-freshwater mixtures or propane as an intermediate or any other suitable heat exchange medium, submerged combustion vaporizers, steam heated vaporizers, or ambient air heated vaporizers and the like. Combinations of these types of vaporizers may be used. Desirably, seawater is used as a heat exchange medium on platform 32. While the natural gas may be re-gasified by any suitable heat exchange method, according to the present invention it is preferred that an open rack vaporizer be used, using seawater as the heat exchange medium. The re-injection pressure of the gas can be achieved as described above by pressurizing the liquefied natural gas prior to re-gasification or by conventional compression equipment of the natural gas after re-gasification or by using both techniques. The natural gas is then passed to an injection platform 36 supported by supports 38 above sea floor 14 where it is injected via a well 40 into a second subterranean formation 44, as shown by arrow 42. Second subterranean formation 44 is capable of storing natural gas and may be a depleted or at least partially depleted subterranean formation which has previously produced gas in sufficient quantities to justify the construction of a system of producing wells, gathering facilities and distribution pipelines for the distribution to a market of natural gas from subterranean formation 44. After and during the injection of the re-gasified liquefied natural gas, production may be achieved from second formation 44 via a well 50, as shown by arrow 52, to a platform 46 which is supported on supports 48 above sea floor 14. Platforms 36 and 46 may be located either on shore as facilities or off shore on platforms. It is, however, desirable that platform 32 be located off shore or near shore to allow for LNG tanker access and offlading and for convenience in the use of seawater as the heat exchange medium.
The produced gas from second formation 44 via platform 46 is passed via a pipeline 54 to a pipeline system 56. It will be understood that platform 46 schematically depicts a plurality of platforms positioned to recover natural gas from subterranean formation 44. Either plurality of platforms or platforms using a plurality of directionally drilled wells or both and the like may be used and the like, as known to those skilled in the art for production of natural gas from a subterranean formation comprising a natural gas field. Similarly, a plurality of gathering lines may be used as shown schematically by pipeline 54. The natural gas, as collected, is then delivered to a pipeline system 56, which is not shown in any detail. It is well understood by those skilled in the art that it may be necessary, and in fact typically is necessary, to treat the recovered natural gas for the removal of hydrogen sulfide and carbon dioxide compounds, water and possibly other contaminants prior to delivering it to a commercial pipeline system.
According to the present invention, the natural gas has been liquefied and can be transported via ship or otherwise over substantial distances from remote gas fields to a re-gasification facility where it is offloaded, pressurized, re-gasified and stored, without the need for cryogenic storage facilities, in a second subterranean formation capable of storing natural gas from which it can be produced through production wells and gathering facilities and a pipeline distribution.
In summary, the present invention represents a remarkably efficient system for producing, transporting, storing and distributing natural gas to a marketplace. The savings are achieved by the use of an existing storage capacity in second formation 44, the use of re-gasification as the LNG is unloaded from tanker 30 to avoid the need for cryogenic storage at platform 32. These advantages result in substantial savings by comparison of the method of the present invention to existing processes for the production and delivery of natural gas from remotely located natural gas fields. The present method also permits the use of sufficient re-gasification capacity to facilitate rapid unloading of a LNG vessel so that the vessel is detained for unloading for a minimal period.
Typically, the natural gas is re-gasified at platform 32 to have an injection temperature slightly above the gas hydrate temperature within the second subterranean formation 44 as injected via well 40 from about 50° F. to about 85° F. The natural gas is injected into the second subterranean reservoir at pressures of between 200 psi and 2500 psi or higher depending upon the depleted reservoir pressure requirement. The conditions for the delivery of natural gas to pipeline 56 are, of course, set by the individual pipeline requirements with respect to pressure, temperature and gas contaminants.
Having thus described the present invention by reference to certain of its preferred embodiments, it is noted that the embodiments disclosed are illustrative rather than limiting in nature and that many variations and modifications are possible within the scope of the present invention. Many such variations and modifications may be considered obvious and desirable by those skilled in the art based upon a review of the foregoing description of preferred embodiments.
Kennelley, Kevin, Patterson, Paul D.
Patent | Priority | Assignee | Title |
10013663, | Dec 09 2011 | ExxonMobil Upstream Research Company | Method for developing a long-term strategy for allocating a supply of liquefied natural gas |
10302254, | Apr 25 2012 | Saudi Arabian Oil Company | Adsorbed natural gas storage facility |
10515426, | Nov 26 2013 | Engie | Method for estimating a characteristic of a liquefied natural gas load |
10539361, | Aug 22 2012 | Woodside Energy Technologies Pty Ltd | Modular LNG production facility |
10704373, | Nov 11 2016 | Halliburton Energy Services, Inc | Storing and de-liquefying liquefied natural gas (LNG) at a wellsite |
10867261, | May 07 2014 | ExxonMobil Upstream Research Company | Method of generating an optimized ship schedule to deliver liquefied natural gas |
10878349, | May 07 2014 | ExxonMobil Upstream Research Company | Method of generating an optimized ship schedule to deliver liquefied natural gas |
11111430, | Feb 05 2018 | Halliburton Energy Services, Inc. | Methane hydrates improved hydrostatic pressure of foam fracturing |
11760446, | Jan 07 2022 | New Fortress Energy | Offshore LNG processing facility |
11828421, | May 31 2018 | TECHNIGAZ, GAZTRANSPORT ET | Method for controlling the filling levels of tanks |
6517286, | Feb 06 2001 | Spectrum Energy Services, LLC | Method for handling liquified natural gas (LNG) |
6546739, | May 23 2001 | Exmar Offshore Company | Method and apparatus for offshore LNG regasification |
6598408, | Mar 29 2002 | Excelerate Energy Limited Parnership | Method and apparatus for transporting LNG |
6739140, | Dec 19 2001 | Conversion Gas Imports, L.P. | Method and apparatus for warming and storage of cold fluids |
6813893, | Dec 19 2001 | Conversion Gas Imports, L.L.C. | Flexible natural gas storage facility |
6829901, | Dec 12 2001 | ExxonMobil Upstream Research Company | Single point mooring regasification tower |
6848502, | Dec 09 2001 | Conversion Gas Imports, L.P. | Method and apparatus for warming and storage of cold fluids |
6880348, | Dec 19 2001 | Conversion Gas Imports, L.P. | Method and apparatus for warming and storage of cold fluids |
6945055, | Dec 19 2001 | Conversion Gas Imports, L.P. | Dual gas facility |
6973948, | Sep 19 2003 | SBM ATLANTIA, INC | Gas offloading system |
7036325, | Dec 19 2001 | Conversion Gas Imports, L.P. | Dual gas facility |
7065974, | Apr 01 2003 | Method and apparatus for pressurizing a gas | |
7219502, | Aug 12 2003 | Excelerate Energy Limited Parnership | Shipboard regasification for LNG carriers with alternate propulsion plants |
7293600, | Feb 27 2002 | Excelerate Energy Limited Parnership | Apparatus for the regasification of LNG onboard a carrier |
7308863, | Aug 22 2003 | Offshore LNG regasification system and method | |
7322387, | Sep 04 2003 | MPEH LLC | Reception, processing, handling and distribution of hydrocarbons and other fluids |
7431622, | Jun 10 2004 | JURONG SHIPYARD PTE LTD | Floating berth system and method |
7451605, | Dec 19 2001 | Conversion Gas Imports, L.P. | LNG receiving terminal that primarily uses compensated salt cavern storage and method of use |
7484371, | Aug 12 2003 | Excelerate Energy Limited Parnership | Shipboard regasification for LNG carriers with alternate propulsion plants |
7624582, | Apr 30 2003 | Remora Technology AS; Torp Technology AS | Cargo evaporation device for use when unloading ships |
7729976, | May 25 2001 | CANATXXENERGY, LLC | Underground gas storage with short term reversible flow operable for use in arbitrage/trading |
7972080, | Mar 14 2007 | AMDG, INC | Bank-sided porosity storage reservoirs |
8069677, | Mar 15 2006 | WOODSIDE ENERGY, LTD | Regasification of LNG using ambient air and supplemental heat |
8074670, | Sep 26 2006 | AMDG, INC | Maintaining dynamic water storage in underground porosity reservoirs |
8156758, | Sep 14 2004 | ExxonMobil Upstream Research Company | Method of extracting ethane from liquefied natural gas |
8402983, | Feb 17 2005 | Single Bouy Moorings, Inc.; SINGLE BUOY MOORINGS, INC | Gas distribution system |
8607580, | Mar 15 2006 | Woodside Energy LTD | Regasification of LNG using dehumidified air |
8959931, | Sep 11 2006 | ExxonMobil Upstream Research Company | Transporting and managing liquefied natural gas |
9562647, | Jan 25 2005 | Framo Engineering AS | Cryogenic fluids transfer system with transfer spills containment |
9562649, | Apr 25 2012 | SAUDI ARAMCO; Saudi Arabian Oil Company | Adsorbed natural gas storage facility |
9919774, | May 20 2010 | Excelerate Energy Limited Partnership | Systems and methods for treatment of LNG cargo tanks |
Patent | Priority | Assignee | Title |
2105383, | |||
2864242, | |||
2975604, | |||
3018632, | |||
3400545, | |||
3400547, | |||
3407606, | |||
3524897, | |||
3535885, | |||
3548024, | |||
3675436, | |||
3849096, | |||
4054433, | Feb 06 1975 | L'Air Liquide, Societe Anonyme pour l'Etude et l'Exploitation des | Incorporated cascade cooling cycle for liquefying a gas by regasifying liquefied natural gas |
4055050, | Feb 11 1976 | Apparatus for and method of regasifying liquefied natural gas | |
4121917, | Sep 09 1975 | UOP, DES PLAINES, IL , A NY GENERAL PARTNERSHIP; KATALISTIKS INTERNATIONAL, INC | Ethylene production with utilization of LNG refrigeration |
6012292, | Jul 16 1998 | Mobil Oil Corporation | System and method for transferring cryogenic fluids |
GB1560096, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Jun 14 2000 | BP Amoco Corporation | (assignment on the face of the patent) | / | |||
Jul 25 2000 | KENNELLEY, KEVIN | BP Amoco Corporation | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 011085 | /0107 | |
Jul 25 2000 | PATTERSON, PAUL D | BP Amoco Corporation | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 011085 | /0107 | |
May 01 2001 | BP Amoco Corporation | BP Corporation North America Inc | CHANGE OF NAME SEE DOCUMENT FOR DETAILS | 012093 | /0870 |
Date | Maintenance Fee Events |
Apr 11 2005 | M1551: Payment of Maintenance Fee, 4th Year, Large Entity. |
Apr 09 2009 | M1552: Payment of Maintenance Fee, 8th Year, Large Entity. |
Apr 09 2013 | M1553: Payment of Maintenance Fee, 12th Year, Large Entity. |
Date | Maintenance Schedule |
Oct 09 2004 | 4 years fee payment window open |
Apr 09 2005 | 6 months grace period start (w surcharge) |
Oct 09 2005 | patent expiry (for year 4) |
Oct 09 2007 | 2 years to revive unintentionally abandoned end. (for year 4) |
Oct 09 2008 | 8 years fee payment window open |
Apr 09 2009 | 6 months grace period start (w surcharge) |
Oct 09 2009 | patent expiry (for year 8) |
Oct 09 2011 | 2 years to revive unintentionally abandoned end. (for year 8) |
Oct 09 2012 | 12 years fee payment window open |
Apr 09 2013 | 6 months grace period start (w surcharge) |
Oct 09 2013 | patent expiry (for year 12) |
Oct 09 2015 | 2 years to revive unintentionally abandoned end. (for year 12) |