An apparatus and method for progressively treating an interval of a wellbore (32) is disclosed. The apparatus comprises a sand control screen (138) that is eccentrically positioned within the wellbore (32) and a fluid delivery tubular (140) that is disposed within the wellbore (32) adjacent to the sand control screen (138). During a treatment process when a treatment fluid is pumped into the fluid delivery tubular (140), the fluid delivery tubular (140) progressively allows the treatment fluid to exit from the interior of the fluid delivery tubular (140) to the exterior of the fluid delivery tubular (140) from a first end (46) of the interval (48) to a second end (44) of the interval (48) to progressively treat the interval (48) of the wellbore (32).
|
49. An apparatus for progressively treating an interval of a wellbore comprising:
a sand control screen eccentrically positioned within the wellbore; and a fluid delivery tubular disposed within the wellbore adjacent to the sand control screen, the fluid delivery tubular including a plurality of propellant members that are progressively combustible from a first end of the interval to a second end of the interval, thereby progressively allowing fluid communication from an interior of the fluid delivery tubular to an exterior of the fluid delivery tubular from the first end of the interval to the second end of the interval.
1. An apparatus for progressively treating an interval of a wellbore comprising:
a sand control screen eccentrically positioned within the wellbore; and a fluid delivery tubular disposed within the wellbore adjacent to the sand control screen, the fluid delivery tubular having a plurality of openings distributed along at least a portion of the length of the fluid delivery tubular, the fluid delivery tubular progressively allowing fluid communication from an interior of the fluid delivery tubular to an exterior of the fluid delivery tubular through the openings from a first end of the interval to a second end of the interval.
23. A method for progressively treating an interval of a wellbore, the method comprising the steps of:
traversing a formation with the wellbore; locating a sand control screen eccentrically within the wellbore proximate the formation; positioning a fluid delivery tubular within the wellbore adjacent to the sand control screen, the fluid delivery tubular having a plurality of openings distributed along at least portion of the length of the fluid delivery tubular; injecting a treatment fluid into the fluid delivery tubular; progressively establishing fluid communication between an interior of the fluid delivery tubular and an exterior of the fluid delivery tabular through the openings from a first end to a second end of the interval; and terminating the injecting.
39. A method for progressively treating an interval of a wellbore, the method comprising the steps of:
traversing a formation with the wellbore; locating a sand control screen eccentrically within the wellbore proximate the formation; positioning a fluid delivery tubular having a plurality of actuatable members operably associated with a plurality of openings distributed along at least a portion of the length of the fluid delivery tubular within the wellbore adjacent to the sand control screen; injecting a treatment fluid into the fluid delivery tubular; progressively actuating the actuatable members to establish fluid communication between an interior of the fluid delivery tubular and an exterior of the fluid delivery tubular from a first end to a second end of the interval; and terminating the injecting.
16. An apparatus for progressively treating an interval of a wellbore comprising:
a sand control screen eccentrically positioned within the wellbore; and a fluid delivery tubular disposed within the wellbore adjacent to the sand control screen, the fluid delivery tubular progressively allowing fluid communication from an interior of the fluid delivery tubular to an exterior of the fluid delivery tubular from a first end of the interval to a second end of the interval through a plurality of pressure actuated actuatable members operably associated with a plurality of openings distributed along at least a portion of the length to the fluid delivery tubular as the pressure created by a treatment fluid pumped into the interior of the fluid delivery tubular progressively increases from the first end of the interval to the second end of the interval.
20. An apparatus for progressively treating an interval of a wellbore comprising:
a sand control screen eccentrically positioned within the wellbore; and a fluid delivery tubular disposed within the wellbore adjacent to the sand control screen, the fluid delivery tubular including a perforated pipe and a plurality of propellant members disposed thereon, each propellant member having a pressure activated firing device associated therewith, the pressure activated firing devices are positioned such that the pressure required to fire the pressure activated firing devices progressively increases from a first end of the interval to a second end of the interval, thereby progressively allowing fluid communication from an interior of the fluid delivery tubular to an exterior of the fluid delivery tubular as the pressure created by a treatment fluid pumped into the interior of the fluid delivery tubular progressively increases from the first end of the interval to the second end of the interval.
46. A method for progressively treating an interval of a wellbore, the method comprising the steps of:
traversing a formation with the wellbore; locating a sand control screen eccentrically within the wellbore proximate the formation; positioning a fluid delivery tubular having a plurality of propellant members distributed along a portion of the length of the fluid delivery tubular within the wellbore adjacent to the sand control screen; injecting a treatment fluid into the fluid delivery tubular; progressively actuating pressure activated firing devices coupled to each propellant member, the pressure activated firing devices being positioned such that the pressure required to fire the pressure activated firing devices progressively increases from the first end to the second end of the interval to progressively establish fluid communication between an interior of the fluid delivery tubular and an exterior of the fluid delivery tubular from a first end to a second end of the interval; and terminating the injecting.
2. The apparatus as recited in
3. The apparatus as recited in
4. The apparatus as recited in
5. The apparatus as recited in
6. The apparatus as recited in
7. The apparatus as recited in
8. The apparatus as recited in
9. The apparatus as recited in
10. The apparatus as recited in
11. The apparatus as recited in
12. The apparatus as recited in
13. The apparatus as recited in
14. The apparatus as recited in
15. The apparatus as recited in
17. The apparatus as recited in
18. The apparatus as recited in
19. The apparatus as recited in
21. The apparatus as recited in
22. The apparatus as recited in
24. The method as recited in
25. The method as recited in
26. The method as recited in
27. The method as recited in
28. The method as recited in
29. The method as recited in
30. The method as recited in
31. The method as recited in
32. The method as recited in
33. The method as recited in
34. The method as recited in
35. The method as recited in
36. The method as recited in
37. The method as recited in
38. The method as recited in
40. The method as recited in
41. The method as recited in
42. The method as recited in
43. The method as recited in
44. The method as recited in
45. The method as recited in
47. The method as recited in
48. The method as recited in
50. The apparatus as recited in
51. The apparatus as recited in
52. The apparatus as recited in
53. The apparatus as recited in
54. The apparatus as recited in
55. The apparatus as recited in
|
This invention relates in general to the treatment of a production interval of a wellbore to stimulate hydrocarbon production and prevent the production of fine particulate materials and, in particular, to an apparatus and method for progressively gravel packing or progressively frac packing the production interval of the wellbore.
It is well known in the subterranean well drilling and completion art that relatively fine particulate materials may be produced during the production of hydrocarbons from a well that traverses an unconsolidated or loosely consolidated formation. Numerous problems may occur as a result of the production of such particulate. For example, the particulate cause abrasive wear to components within the well, such as tubing, pumps and valves. In addition, the particulate may partially or fully clog the well creating the need for an expensive workover. Also, if the particulate matter is produced to the surface, it must be removed from the hydrocarbon fluids using surface processing equipment.
One method for preventing the production of such particulate material is to gravel pack the well adjacent the unconsolidated or loosely consolidated production interval. In a typical gravel pack completion, a sand control screen is lowered into the wellbore on a work string to a position proximate the desired production interval. A fluid slurry including a liquid carrier and a relatively coarse particulate material, such as sand, gravel or proppants which are typically sized and graded and which are typically referred to herein as gravel, is then pumped down the work string and into the well annulus formed between the sand control screen and the perforated well casing or open hole production zone.
The liquid carrier either flows into the formation or returns to the surface by flowing through a wash pipe or both. In either case, the gravel is deposited around the sand control screen to form the gravel pack, which is highly permeable to the flow of hydrocarbon fluids but blocks the flow of the fine particulate materials carried in the hydrocarbon fluids. As such, gravel packs can successfully prevent the problems associated with the production of these particulate materials from the formation.
It is sometimes desirable to perform a formation fracturing and propping operation prior to or simultaneously with the gravel packing operation. Hydraulic fracturing of a hydrocarbon formation is sometimes necessary to increase the permeability of the production interval adjacent the wellbore. According to conventional practice, a fracture fluid such as water, oil, oil/water emulsion, gelled water or gelled oil is pumped down the work string with sufficient volume and pressure to open multiple fractures in the production interval. The fracture fluid may carry a suitable propping agent, such as sand, gravel or proppants, which are typically referred to herein as proppants, into the fractures for the purpose of holding the fractures open following the fracturing operation.
The fracture fluid must be forced into the formation at a flow rate great enough to fracture the formation allowing the entrained proppant to enter the fractures and prop the formation structures apart, producing channels which will create highly conductive paths reaching out into the production interval, and thereby increasing the reservoir permeability in the fracture region. As such, the success of the fracture operation is dependent upon the ability to inject large volumes of hydraulic fracture fluid along the entire length of the formation at a high pressure and at a high flow rate.
It has been found that it is difficult to achieve a complete gravel pack of the desired production interval either independent of or as part of a fracturing operation, particularly in long or inclined/horizontal production intervals. These incomplete packs are commonly a result of the liquid carrier entering the permeable portions of the production interval causing the gravel to form a sand bridge in the annulus. Thereafter, the sand bridge prevents the gravel pack slurry from flowing to the remainder of the annulus which, in turn, prevents the placement of sufficient gravel in the remainder of the annulus.
Therefore a need has arisen for an apparatus and method that are capable of creating fractures along the entire length of a production interval. A need has also arisen for such an apparatus and method that can produce a complete gravel pack of the wellbore adjacent to the production interval either independent of or as part of the fracturing of the production interval. Further, a need has arisen for an apparatus and method that are capable of stimulating the production interval to enhance production and gravel packing the production interval to prevent the production of fine particulate materials when production commences.
The present invention disclosed herein comprises an apparatus and method that is capable of enhancing production from a production interval by creating fractures throughout the entire interval and producing a substantially complete gravel pack of the wellbore adjacent to the production interval to prevent the production of fine particulate materials when production commences. The apparatus and method of the present invention achieves these results by progressively treating the production interval from one end to the other.
The apparatus comprises a sand control screen that is positioned within the wellbore and a fluid delivery tubular positioned adjacent to sand control screen in the wellbore. The fluid delivery tubular progressively allows fluid communication from the interior of the fluid delivery tubular to the exterior of fluid delivery tubular from a first end to a second end of the interval, thereby delivering the treatment fluid along the entire length of the interval.
The fluid delivery tubular may comprises a plurality of actuatable members. The actuatable devices may be rupture disks, pressure actuated one-way valves or other pressure actuated devices that are positioned along a portion of the length of the fluid delivery tubular such that the pressure required to actuate the actuatable members progressively increases from the first end to the second end of the interval. Alternatively, the actuatable device may be progressively actuated from the first end to the second end of the interval using signals sent from the surface using hard wire connections, fiber optics, hydraulics or wireless telemetry.
The fluid delivery tubular may alternatively comprise a perforated pipe having a plurality of removable members positioned on the interior or the exterior thereof. The removable members may be propellants or other combustible material members each having an initiator. The initiators may be activated using signals. Alternatively, the initiators may have pressure activated firing devices that are positioned such that the pressure required to fire the pressure activated firing devices progressively increasing from the first end to the second end of the interval.
The removable members may alternatively be friable members that are progressively removable from the first end to the second end of the interval. Each friable member may include a pressure actuated vibration generator. In this case, the pressure actuated vibration generators are positioned such that the pressure required to activate the pressure actuated vibration generators progressively increasing from the first end to the second end of the interval. Alternatively, each of the friable members may have a vibration generator that activated by a signal sent from the surface.
The method of the present invention comprises traversing the formation with the wellbore, locating a sand control screen eccentrically within the wellbore proximate the formation, positioning a fluid delivery tubular adjacent to the sand control screen within the wellbore, injecting a treatment fluid into the fluid delivery tubular, progressively establishing fluid communication between the interior of the fluid delivery tubular and the exterior of the fluid delivery tubular from the first end to the second end of the interval and terminating the injecting when the interval is treated.
For a more complete understanding of the features and advantages of the present invention, reference is now made to the detailed description of the invention along with the accompanying figures in which corresponding numerals in the different figures refer to corresponding parts and in which:
While the making and using of various embodiments of the present invention are discussed in detail below, it should be appreciated that the present invention provides many applicable inventive concepts which can be embodied in a wide variety of specific contexts. The specific embodiments discussed herein are merely illustrative of specific ways to make and use the invention, and do not delimit the scope of the present invention.
Referring initially to
A wellbore 32 extends through the various earth strata including formation 14. A casing 34 is cemented within wellbore 32 by cement 36. Work string 30 includes various tools including a sand control screen assembly 38 which is positioned within wellbore 32 adjacent to formation 14. Also extending from platform 12 through wellbore 32 is a fluid delivery tubular 40 having a fluid discharge section 42 positioned adjacent to formation 14 which is used to frac pack or gravel pack the production interval 48 between packers 44, 46. When it is desired to treat interval 48, work string 30 and fluid delivery tubular 40 are lowered through casing 34 until sand control screen assembly 38 and fluid discharge section 42 are positioned adjacent to formation 14 including perforations 50. Thereafter, a treatment fluid containing sand, gravel, proppants or the like is pumped down delivery tubular 40 to progressively treat interval 48.
Even though
Referring now to
In the illustrated embodiment, fluid discharge section 42 of fluid delivery tubular 40 includes a plurality of progressively actuatable members 60A-60E. Suitable actuatable members 60A-60E include rupture disks or valves and are preferably one-way valves that selectively allow fluid to flow from the interior of fluid delivery tubular 40 to the exterior of fluid delivery tubular 40. Actuatable members 60A-60E may be progressively actuated using a variety of known techniques such as sending a signal via a direct electrical connection, fiber optics, hydraulics, wireless telemetry including pressure pulses, electromagnetic waves or acoustic signals and the like. Actuatable members 60A-60E are preferably pressure actuated one-way valves as explained in more detail below.
To begin the completion process, interval 48 adjacent to formation 14 is isolated. Packer 44 seals the near end of interval 48 and packer 46 seals the far end of interval 48. Cross-over assembly 54 is located adjacent to screen assembly 38, traversing packer 44 with portions of cross-over assembly 54 on either side of packer 44. As illustrated, when the treatment operation is a gravel pack, the objective is to uniformly and completely fill interval 48 with gravel. To help achieve this result, wash pipe 52 is disposed within screen assembly 38. Wash pipe 52 extends into cross-over assembly 54 such that return fluid passing through screen assembly 38, indicated by arrows 62, may travel through wash pipe 52, as indicated by arrow 64, and into annulus 66, as indicted by arrow 68, for return to the surface.
The fluid slurry containing gravel 70 is pumped down fluid delivery tubular 40. In the illustrated embodiment, the fluid slurry containing gravel 70 travels to the far end of interval 48 through fluid delivery tubular 40. As illustrated, a portion of fluid slurry containing gravel 70 exits the open end of fluid delivery tubular 40. As gravel 70 builds up at the far end of interval 48, the pressure within fluid delivery tubular 40 will begin to increase. Alternatively, the far end of fluid delivery tubular 40 could be closed in which case the pressure also increases in fluid delivery tubular 40 when the fluid slurry containing gravel travels to the far end.
Once the pressure in fluid delivery tubular 40 increases to a sufficient level, the progressive operation of the present invention may begin. Specifically, as best seen in
As the initial portion of the gravel pack becomes tightly packed, the pressure in fluid deliver tubular 40 again increases. At this point and as best seen in
As this portion of the gravel pack becomes tightly packed, the pressure in fluid delivery tubular 40 again increases. At this point and as best seen in
This process continues to progress from the far end of interval 48 toward the near end of interval 48. Specifically, as best seen in
As this portion of the gravel pack becomes tightly packed, the pressure in fluid delivery tubular 40 again increases. At this point and as best seen in
As can be seen, using the present invention for progressively treating an interval of a wellbore, a gravel pack may progress from one end of an interval toward the other end of an interval as fluid communication is progressively established along the entire length of the interval. Also, as should be apparent to those skilled in the art, even though
Likewise, even though
As stated above, there are numerous ways to progressively actuate actuatable members 60A-60E. In the preferred method described above, the pressure created by the fluid slurry within fluid delivery tubular 40 progressively triggers the actuation of actuatable members 60A-60E. One way to implement this method is to position actuatable members 60A-60E within fluid delivery tubular 40 such that the pressure required to actuate actuatable members 60A-60E progressively increases from the one end of interval 48 to the other end of interval 48. For example, each adjacent actuatable member may be set to actuate at an incremental pressure above the prior actuatable members such as at increments of between about 50-100 psi. This assures a proper progression of the gravel pack by preventing any out of sequence activations. In addition, this approach is particularly advantageous in that the incremental pressure increase of adjacent actuatable members helps to insure that each section of the gravel pack is tightly packed prior to initiating the gravel packing of subsequent sections.
Alternatively, a hard wired or wireless telemetry system may be used to progressively actuate actuatable members 60A-60E. For example, each actuatable member may be actuated by sending a signal addressed to a specific actuatable member. This assures a proper progression of the gravel pack by preventing any out of sequence activations. The signals may be manually or automatically sent based upon time or the pressure response in fluid delivery tubular 40. For example, the signal to actuate the next actuatable member may be sent each time the pressure within fluid delivery tubular 40 reaches a particular level or each time the pressure within fluid delivery tubular 40 reaches the next preselected pressure increment. As with the direct pressure response method, the particular actuation sequence should insure that each section of the gravel pack is tightly packed prior to initiating the gravel packing of subsequent sections.
Referring now to
In the illustrated embodiment, fluid discharge section 142 of fluid delivery tubular 140 includes a plurality of progressively actuatable members 160A-160E which are preferable valves, such as pressure actuated one-way valves that selectively allow fluid to flow from the interior of fluid delivery tubular 140 to the exterior of fluid delivery tubular 140. Actuatable members 160A-160E may alternatively be progressively actuated using a variety of known techniques such as sending a signal via a hard wire connection, fiber optics, hydraulics, wireless telemetry including pressure pulses, electromagnetic waves or acoustic signals and the like.
To begin the completion process, interval 48 adjacent to formation 14 is isolated. Packer 44 seals the near end of interval 48 and packer 46 seals the far end of interval 48. Cross-over assembly 154 is located adjacent to screen assembly 138, traversing packer 44 with portions of cross-over assembly 154 on either side of packer 44. As illustrated, when the treatment operation is a frac pack, the objective is to enhance the permeability of formation 14 by delivering a fluid slurry containing proppants 170 at a high flow rate and in a large volume above the fracture gradient of formation 14 such that fractures may be formed within formation 14 and held open by the proppants 170. In addition, a frac pack also has the objective of preventing the production of fines by packing interval 48 with the proppants 170. To help achieve these results, valve 150 of cross-over assembly 154 is initially in the closed position to prevent returns from flowing therethrough.
The fluid slurry containing proppants 170 is pumped down-fluid delivery tubular 140. In the illustrated embodiment, the fluid slurry containing proppants 170 travels to the far end of interval 48 through fluid delivery tubular 140. At this point, the fluid slurry containing proppants 170 may exit the far end of fluid delivery tubular 140 if it is open or builds up in fluid delivery tubular 140 if it is closed at the far end. In either case, the pressure within fluid delivery tubular 140 will begin to increase.
Once the pressure in fluid delivery tubular 140 increases to a sufficient level, the progressive operation of the present invention may begin. Specifically, as best seen in
Referring now to
In the illustrated embodiment, fluid discharge section 242 of fluid delivery tubular 240 includes a plurality of perforations 244A-244J that are selective blocked by removable members 260A-260E. Removable members 260A-260E may be constructed from a variety of materials such as combustible materials, referred to herein as propellants, that are removable by combustion, friable materials, including ceramics, that are removable by disintegration, or other materials that are removable in a downhole environment.
When removable members 260A-260E are constructed from propellants, suitable initiators are attached to each removable member 260A-260E such that the combustion process of each removable member 260A-260E may be triggered independently. The initiators may be operated using a variety of known techniques including pressure actuation, electrical actuation, acoustic actuation or the like. For example, as explained in more detail below, the pressure generated by the treatment fluid can be used to trigger the initiators. Alternatively, a signal may be sent to trigger each of the removeable members 260A-260E via a hard wired connection, fiber optics, hydraulics, a wireless telemetry system utilizing pressure pulses, electromagnetic waves or acoustic signals and the like.
When removable members 260A-260E are constructed from friable materials, suitable vibration generators are attached to each removable member 260A-260E such that the disintegration process of each removable member 260A-260E may be triggered independently. The vibration generators may be operated using a variety of known techniques such as those described above.
To begin the completion process, interval 48 adjacent to formation 14 is isolated. Packer 44 seals the near end of interval 48 and packer 46 seals the far end of interval 48. Cross-over assembly 254 is located adjacent to screen assembly 238, traversing packer 44 with portions of cross-over assembly 254 on either side of packer 44. As illustrated, when the treatment operation is a gravel pack, the objective is to uniformly and completely fill interval 48 with gravel. To help achieve this result, wash pipe 252 is disposed within screen assembly 238. Wash pipe 252 extends into cross-over assembly 254 such that return fluid passing through screen assembly 238, indicated by arrows 262, may travel through wash pipe 252, as indicated by arrow 264, and into annulus 66, as indicted by arrow 268, for return to the surface.
The fluid slurry containing gravel 70 is pumped down fluid delivery tubular 240. In the illustrated embodiment, the fluid slurry containing gravel 70 travels to the far end of interval 48 through fluid delivery tubular 240. At this point, a portion of fluid slurry containing gravel 70 exits the open end of the fluid delivery tubular 240 if this end is open to flow.
As the pressure in fluid delivery tubular 240 increases to a sufficient level, the progressive operation of the present invention may begin. Specifically, removable member 260A is removed which allows the fluid slurry containing gravel 70 to travel from fluid delivery tubular 40 through perforations 244A-244B into interval 48. As the fluid slurry containing gravel 70 enters interval 48, the gravel 70 drops out of the slurry and builds up from formation 14, filling perforation 50A and interval 48 around the end section of screen assembly 238 forming the initial portion of the gravel pack. Some of the carrier fluid in the slurry may leak off through perforation 50A into formation 14 while the remainder of the carrier fluid passes through screen assembly 238, as indicated by arrows 262, that is sized to prevent gravel 70 from flowing therethrough. The fluid flowing back through screen assembly 238, as explained above, follows the paths indicated by arrows 264, 268 back to the surface.
As the pressure within fluid delivery tubular 140 increases, removable member 260B is removed which allows fluid flow through perforations 244C-244D into interval 48 which packs perforation 50B and the section of screen assembly 238 adjacent thereto. This process progresses from the far end of interval 48 to the near end of interval 48 by progressively removing removable member 260C, which exposes perforations 244E-244F, removable member 260D, which exposes perforations 244G-244H, and removable member 260E, which exposes perforations 244I-244J. Accordingly, the entire interval 48 is progressively gravel packed. After the treatment process is completed, a valve (not pictured) in fluid delivery tubular 240 may be closed to prevent the flow of fluids, for example production fluids, to the surface therethrough.
As stated above, there are numerous ways to remove removable members 260 from fluid discharge section 242 of fluid delivery tubular 240 to progressively establish fluid communication between the interior of fluid delivery tubular 240 and the exterior of fluid delivery tubular 240. One preferred method allows the pressure created by the treatment fluid within fluid delivery tubular 240 to progressively trigger the removal of removable members 260. For example, when the removable members 260 are constructed of propellant material, pressure activated firing devices may be attached to initiators that are coupled on each of the removable members 260. The pressure activated firing devices are then positioned within fluid delivery tubular 240 such that the pressure required to fire the pressure activated firing devices progressively increases from, for example, the far end of interval 48 toward the near end of interval 48. Each adjacent pressure activated firing device may be set to fire at an incremental pressure above the prior pressure activated firing device such as at increments of between about 50-100 psi. This assures a proper progression of the gravel pack by preventing any out of sequence activations. In addition, this approach is particularly advantageous in that the incremental pressure increase of adjacent pressure activated firing devices helps to insure that each section of the gravel pack is tightly packed prior to initiating the gravel packing of subsequent sections.
Alternatively, a signal may be used to progressively trigger the removal of removable member 260. For example, when the removable members 260 are constructed of a friable material, vibration generators may be coupled on each of the removable members 260. Each vibration generator may be activated by a particular signal addressed specifically for that vibration generator. This assures a proper progression of the gravel pack by preventing any out of sequence activations. The signals may be manually or automatically sent based upon time or the pressure response in fluid delivery tubular 240. For example, the signal to remove the next removable member 260 may be sent each time the pressure within fluid delivery tubular 240 reaches a particular level or each time the pressure within fluid delivery tubular 240 reaches the next preselected pressure increment. As with the direct pressure response method, the particular removal sequence should insure that each section of the gravel pack is tightly packed prior to initiating the gravel packing of subsequent sections.
Even though
While this invention has been described with reference to illustrative embodiments, this description is not intended to be construed in a limiting sense. Various modifications and combinations of the illustrative embodiments as well as other embodiments of the invention, will be apparent to persons skilled in the art upon reference to the description. It is, therefore, intended that the appended claims encompass any such modifications or embodiments.
Schultz, Roger L., Dusterhoft, Ronald G., Hamid, Syed, Michael, Robert Ken
Patent | Priority | Assignee | Title |
10344583, | Aug 30 2016 | ExxonMobil Upstream Research Company | Acoustic housing for tubulars |
10364669, | Aug 30 2016 | ExxonMobil Upstream Research Company | Methods of acoustically communicating and wells that utilize the methods |
10408047, | Jan 26 2015 | ExxonMobil Upstream Research Company | Real-time well surveillance using a wireless network and an in-wellbore tool |
10415376, | Aug 30 2016 | ExxonMobil Upstream Research Company | Dual transducer communications node for downhole acoustic wireless networks and method employing same |
10465505, | Aug 30 2016 | ExxonMobil Upstream Research Company | Reservoir formation characterization using a downhole wireless network |
10487647, | Aug 30 2016 | ExxonMobil Upstream Research Company | Hybrid downhole acoustic wireless network |
10526888, | Aug 30 2016 | ExxonMobil Upstream Research Company | Downhole multiphase flow sensing methods |
10590759, | Aug 30 2016 | ExxonMobil Upstream Research Company | Zonal isolation devices including sensing and wireless telemetry and methods of utilizing the same |
10690794, | Nov 17 2017 | ExxonMobil Upstream Research Company | Method and system for performing operations using communications for a hydrocarbon system |
10697287, | Aug 30 2016 | ExxonMobil Upstream Research Company | Plunger lift monitoring via a downhole wireless network field |
10697288, | Oct 13 2017 | ExxonMobil Upstream Research Company | Dual transducer communications node including piezo pre-tensioning for acoustic wireless networks and method employing same |
10711600, | Feb 08 2018 | ExxonMobil Upstream Research Company | Methods of network peer identification and self-organization using unique tonal signatures and wells that use the methods |
10724363, | Oct 13 2017 | ExxonMobil Upstream Research Company | Method and system for performing hydrocarbon operations with mixed communication networks |
10837276, | Oct 13 2017 | ExxonMobil Upstream Research Company | Method and system for performing wireless ultrasonic communications along a drilling string |
10844708, | Dec 20 2017 | ExxonMobil Upstream Research Company | Energy efficient method of retrieving wireless networked sensor data |
10883363, | Oct 13 2017 | ExxonMobil Upstream Research Company | Method and system for performing communications using aliasing |
11035226, | Oct 13 2017 | ExxoMobil Upstream Research Company | Method and system for performing operations with communications |
11156081, | Dec 29 2017 | ExxonMobil Upstream Research Company | Methods and systems for operating and maintaining a downhole wireless network |
11180986, | Sep 12 2014 | ExxonMobil Upstream Research Company | Discrete wellbore devices, hydrocarbon wells including a downhole communication network and the discrete wellbore devices and systems and methods including the same |
11203927, | Nov 17 2017 | ExxonMobil Upstream Research Company | Method and system for performing wireless ultrasonic communications along tubular members |
11268378, | Feb 09 2018 | ExxonMobil Upstream Research Company | Downhole wireless communication node and sensor/tools interface |
11293280, | Dec 19 2018 | ExxonMobil Upstream Research Company | Method and system for monitoring post-stimulation operations through acoustic wireless sensor network |
11313215, | Dec 29 2017 | ExxonMobil Upstream Research Company | Methods and systems for monitoring and optimizing reservoir stimulation operations |
11828172, | Aug 30 2016 | EXXONMOBIL TECHNOLOGY AND ENGINEERING COMPANY | Communication networks, relay nodes for communication networks, and methods of transmitting data among a plurality of relay nodes |
6789624, | May 31 2002 | Halliburton Energy Services, Inc | Apparatus and method for gravel packing an interval of a wellbore |
6932157, | Mar 06 2001 | Halliburton Energy Services, Inc. | Apparatus and method for treating an interval of a wellbore |
6978840, | Feb 05 2003 | Halliburton Energy Services, Inc. | Well screen assembly and system with controllable variable flow area and method of using same for oil well fluid production |
7100691, | Aug 14 2001 | Halliburton Energy Services, Inc. | Methods and apparatus for completing wells |
7147054, | Sep 03 2003 | Schlumberger Technology Corporation | Gravel packing a well |
7243724, | Mar 06 2001 | Halliburton Energy Services, Inc | Apparatus and method for treating an interval of a wellbore |
7703520, | Jan 08 2008 | Halliburton Energy Services, Inc. | Sand control screen assembly and associated methods |
7712529, | Jan 08 2008 | Halliburton Energy Services, Inc | Sand control screen assembly and method for use of same |
7806184, | May 09 2008 | WAVEFRONT TECHNOLOGY SERVICES INC | Fluid operated well tool |
7814973, | Aug 29 2008 | Halliburton Energy Services, Inc | Sand control screen assembly and method for use of same |
7841409, | Aug 29 2008 | Halliburton Energy Services, Inc | Sand control screen assembly and method for use of same |
7866383, | Aug 29 2008 | Halliburton Energy Services, Inc | Sand control screen assembly and method for use of same |
8056638, | Feb 22 2007 | MCR Oil Tools, LLC | Consumable downhole tools |
8210257, | Mar 01 2010 | Halliburton Energy Services Inc. | Fracturing a stress-altered subterranean formation |
8256521, | Jun 08 2006 | Halliburton Energy Services Inc. | Consumable downhole tools |
8272446, | Jun 08 2006 | Halliburton Energy Services Inc. | Method for removing a consumable downhole tool |
8291970, | Jun 08 2006 | MCR Oil Tools, LLC | Consumable downhole tools |
8291972, | Aug 29 2008 | Halliburton Energy Services, Inc. | Sand control screen assembly and method for use of same |
8322449, | Feb 22 2007 | Halliburton Energy Services, Inc.; MCR Oil Tools, LLC | Consumable downhole tools |
8499827, | Aug 29 2008 | Halliburton Energy Services, Inc. | Sand control screen assembly and method for use of same |
8584753, | Nov 03 2010 | Halliburton Energy Services, Inc | Method and apparatus for creating an annular barrier in a subterranean wellbore |
9428988, | Jun 17 2011 | Nine Downhole Technologies, LLC | Hydrocarbon well and technique for perforating casing toe |
Patent | Priority | Assignee | Title |
1975162, | |||
2342913, | |||
2344909, | |||
4102395, | Feb 16 1977 | H W S -82, INC , A CORP OF TX | Protected well screen |
4553595, | Jun 01 1984 | Texaco Inc. | Method for forming a gravel packed horizontal well |
4558742, | Jul 13 1984 | Texaco Inc. | Method and apparatus for gravel packing horizontal wells |
4646839, | Nov 23 1984 | Exxon Production Research Co. | Method and apparatus for through-the-flowline gravel packing |
4945991, | Aug 23 1989 | Mobile Oil Corporation | Method for gravel packing wells |
5082052, | Jan 31 1991 | Mobil Oil Corporation | Apparatus for gravel packing wells |
5113935, | May 01 1991 | Mobil Oil Corporation | Gravel packing of wells |
5161613, | Aug 16 1991 | Mobil Oil Corporation | Apparatus for treating formations using alternate flowpaths |
5161618, | Aug 16 1991 | Mobil Oil Corporation | Multiple fractures from a single workstring |
5332039, | Dec 07 1992 | Texaco Inc. | Selective dual gravel pack |
5333688, | Jan 07 1993 | Mobil Oil Corporation | Method and apparatus for gravel packing of wells |
5355956, | Sep 28 1992 | Halliburton Company | Plugged base pipe for sand control |
5390966, | Oct 22 1993 | Mobil Oil Corporation | Single connector for shunt conduits on well tool |
5419394, | Nov 22 1993 | Mobil Oil Corporation | Tools for delivering fluid to spaced levels in a wellbore |
5443117, | Feb 07 1994 | Halliburton Company | Frac pack flow sub |
5476143, | Apr 28 1994 | ExxonMobil Upstream Research Company | Well screen having slurry flow paths |
5515915, | Apr 10 1995 | Mobil Oil Corporation | Well screen having internal shunt tubes |
5588487, | Sep 12 1995 | Mobil Oil Corporation | Tool for blocking axial flow in gravel-packed well annulus |
5636691, | Sep 18 1995 | Halliburton Company | Abrasive slurry delivery apparatus and methods of using same |
5755286, | Dec 20 1995 | Ely and Associates, Inc. | Method of completing and hydraulic fracturing of a well |
5842516, | Apr 04 1997 | Mobil Oil Corporation | Erosion-resistant inserts for fluid outlets in a well tool and method for installing same |
5848645, | Sep 05 1996 | Mobil Oil Corporation | Method for fracturing and gravel-packing a well |
5868200, | Apr 17 1997 | WEATHERFORD TECHNOLOGY HOLDINGS, LLC | Alternate-path well screen having protected shunt connection |
5890533, | Jul 29 1997 | Mobil Oil Corporation | Alternate path well tool having an internal shunt tube |
5921318, | Apr 21 1997 | Halliburton Energy Services, Inc | Method and apparatus for treating multiple production zones |
5934376, | Oct 16 1997 | Halliburton Energy Services, Inc | Methods and apparatus for completing wells in unconsolidated subterranean zones |
6003600, | Oct 16 1997 | Halliburton Energy Services, Inc | Methods of completing wells in unconsolidated subterranean zones |
6047773, | Aug 09 1996 | Halliburton Energy Services, Inc | Apparatus and methods for stimulating a subterranean well |
6059032, | Dec 10 1997 | Mobil Oil Corporation | Method and apparatus for treating long formation intervals |
6116343, | Feb 03 1997 | Halliburton Energy Services, Inc | One-trip well perforation/proppant fracturing apparatus and methods |
6125933, | Sep 18 1997 | Halliburton Energy Services, Inc. | Formation fracturing and gravel packing tool |
6220345, | Aug 19 1999 | Schlumberger Technology Corporation | Well screen having an internal alternate flowpath |
6227303, | Apr 13 1999 | Mobil Oil Corporation | Well screen having an internal alternate flowpath |
6230803, | Dec 03 1998 | Baker Hughes Incorporated | Apparatus and method for treating and gravel-packing closely spaced zones |
6343651, | Oct 18 1999 | Schlumberger Technology Corporation | Apparatus and method for controlling fluid flow with sand control |
6397950, | Nov 21 1997 | Halliburton Energy Services, Inc | Apparatus and method for removing a frangible rupture disc or other frangible device from a wellbore casing |
6446729, | Oct 18 1999 | Schlumberger Technology Corporation | Sand control method and apparatus |
6450263, | Dec 01 1998 | Halliburton Energy Services, Inc | Remotely actuated rupture disk |
6464007, | Aug 22 2000 | ExxonMobil Oil Corporation | Method and well tool for gravel packing a long well interval using low viscosity fluids |
6494261, | Aug 16 2000 | Halliburton Energy Services, Inc | Apparatus and methods for perforating a subterranean formation |
6588507, | Jun 28 2001 | Halliburton Energy Services, Inc | Apparatus and method for progressively gravel packing an interval of a wellbore |
EP1132571, | |||
WO61913, | |||
WO114691, | |||
WO144619, | |||
WO210554, | |||
WO9912630, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Oct 22 2001 | Halliburton Energy Services, Inc. | (assignment on the face of the patent) | / | |||
Jan 02 2002 | MICHAEL, ROBERT KEN | Halliburton Energy Services, Inc | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 012579 | /0881 | |
Jan 03 2002 | SCHULTZ, ROGER L | Halliburton Energy Services, Inc | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 012579 | /0881 | |
Jan 09 2002 | DUSTERHOFT, RONALD G | Halliburton Energy Services, Inc | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 012579 | /0881 | |
Jan 28 2002 | HAMID, SYED | Halliburton Energy Services, Inc | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 012579 | /0881 |
Date | Maintenance Fee Events |
May 10 2004 | ASPN: Payor Number Assigned. |
Sep 17 2007 | REM: Maintenance Fee Reminder Mailed. |
Mar 09 2008 | EXP: Patent Expired for Failure to Pay Maintenance Fees. |
Date | Maintenance Schedule |
Mar 09 2007 | 4 years fee payment window open |
Sep 09 2007 | 6 months grace period start (w surcharge) |
Mar 09 2008 | patent expiry (for year 4) |
Mar 09 2010 | 2 years to revive unintentionally abandoned end. (for year 4) |
Mar 09 2011 | 8 years fee payment window open |
Sep 09 2011 | 6 months grace period start (w surcharge) |
Mar 09 2012 | patent expiry (for year 8) |
Mar 09 2014 | 2 years to revive unintentionally abandoned end. (for year 8) |
Mar 09 2015 | 12 years fee payment window open |
Sep 09 2015 | 6 months grace period start (w surcharge) |
Mar 09 2016 | patent expiry (for year 12) |
Mar 09 2018 | 2 years to revive unintentionally abandoned end. (for year 12) |