A pre-fabricated warped pavement slab and a forming system for making the slabs. The forming system includes a plurality of forming sections which can be adjusted so as to form a warped-plane pavement slab. Also disclosed are methods for making the pavement slab and forming system. Also disclosed is a method for installing the warped pavement slab.
|
9. A system for forming a pre-fabricated warped pavement slab, said slab including a top surface, said system comprising:
a form system including a plurality of attached form sections having an edge, and support beams; a jacking beam and a jack and three corners in a first plane configured to receive a hardenable, flowable material, further wherein said form system is configurable so as to form said warped pavement slab wherein said top surface of said warped pavement slab is warped to be parallel to a bottom surface of said warped pavement slab, wherein the warp of the form system is adjusted by raising or lowering said jacking beam on said edge of said form system to move a fourth corner on the form system to a second plane.
11. A system for making a pre-fabricated pavement slab formed of a hardenable, flowable material, comprising:
a plurality of form sections flexibly attached to each other and having sides and corners, wherein said sections are configured to form a warped slab, said plurality of form sections make a top surface of said slab warped by raising or lowering a portion of said plurality of form sections with the sides of the form sections remaining straight when one corner is moved out of plane to warp the form, further wherein if a non-perpendicular cross-section having resultant edges is taken out of the slab produced by said plurality of form sections, the resultant edges will be non-linear, wherein said resultant edges is the line at a top surface or bottom surface of the cross-sectional cut of the slab.
12. A method for making a pre-fabricated warped pavement slab forming system comprising:
providing a plurality of side rails attached to each other and said side rails having a first side and a second side having an edge that is positionable for forming the pre-fabricated warped pavement slab from a hardenable, flowable material;
providing a casting deck having a plurality of form sections to attach said side rails;
providing a device for adjusting a warped plane of the plurality of form sections configured to raise or lower an edge of said plurality of form sections; and
warping said plurality of form sections by moving a plurality of spaced stiffeners from a first set of slopes to a second set of slopes to adjust the warped plane by raising or lowering a portion of said plurality of spaced stiffeners so that the forms produce the pre-fabricated warped pavement slab having a cross sectional slope that varies linearly along a length of the slab when the cross sectional slope is taken perpendicular to a side of the slab.
1. A system for forming a pre-fabricated warped pavement slab comprising:
a plurality of individual form sections for forming a pre-fabricated pavement slab, said plurality of individual form sections including a plurality of spaced stiffeners that are flexibly affixed to each other, wherein said plurality of spaced stiffeners are moveable by raising or lowering to create a warp;
a device for adjusting the slopes of the plurality of the spaced stiffeners, wherein said device for adjusting the slopes is configured to be positionable and alignable at an angle across said spaced stiffeners such that when said device for adjusting the slopes is moved either by raising or lowering said plurality of spaced stiffeners from a set of the first set of slopes to a second set of slopes, the slope of each of the moved spaced stiffeners will each be at a different slope with respect to each of the other moved spaced stiffeners; and
a plurality of side rails positioned on said individual form sections for receiving hardenable, flowable material.
2. A system as in
4. A system as in
5. A system as in
6. A system as in
7. A system as in
8. A system as in
10. The system of
|
This application claims benefit to U.S. application Ser. No. 10/185,821, filed Jun. 27, 2002, now U.S. Pat. No. 6,899,489, which claims benefit to U.S. Pat. Provisional Application Ser. No. 60/339,703 filed Dec. 12, 2001.
1. Technical Field
The present invention relates generally to roadway construction and repair, and more particularly, to the formation, installation and system for making and attaching a pre-fabricated warped pavement slab, and the warped slab so formed.
2. Related Art
Heretofore, attempts have been made to construct and install pre-fabricated or precast pavement slabs. However, most attempts have been unsuccessful due to a combination of factors. For example, it is difficult to prepare and maintain a perfectly smooth sub-grade which is necessary to uniformly support the slab. It is even more difficult to prepare a subgrade that is warped meeting profile and cross-slope changes normally encountered in roadway construction. Attempts to make a pre-fabricated pavement slab with an accurate and predictable warp have been unsuccessful. Likewise, it is difficult to connect adjacent slabs in a manner that uniformly transfers shear loading from one slab to the next. Heretofore attempts to prefabricate such pavement slabs have been of an experimental nature and have been entirely inadequate and inefficient. Accordingly, there exists a need in the industry for a pre-fabricated warped pavement slab and a method of installing the warped slab that solves these and other problems.
A first general aspect of the present invention provides an apparatus comprising: a pre-fabricated pavement slab formed of a hardenable, flowable material, wherein said pre-fabricated pavement slab is warped.
A second general aspect of the present invention provides a system for forming a pre-fabricated pavement slab comprising: a plurality of form sections for forming a hardenable, flowable material; and a device for adjusting a warp of the form sections.
A third general aspect of the present invention provides a method of marking a pre-fabricated pavement slab comprising: providing a plurality of form sections; adjusting a first portion of the plurality of form sections out of place with a second portion of the plurality of form sections; and placing a hardenable, flowable material onto the form sections.
A fourth general aspect of the present invention provides a method of making a prefabricated pavement slab forming system comprising: providing a plurality of form sections for forming hardenable, flowable material; and providing a device for adjusting a warp of the form sections.
A fifth general aspect of the present invention provides a method for installing a pre-fabricated warped pavement slab comprising: placing a pre-fabricated warped pavement slab on a graded subbase; and placing a binder material between a bottom surface of the warped slab and the graded subbase.
A sixth general aspect of the present invention provides a pavement system comprising: a graded subbase; a plurality of pre-fabricated warped pavement slabs placed on the graded subbase; a binder distribution system attached to a bottom surface of the plurality of pre-fabricated warped pavement slabs; and an interconnection system along edges of the plurality of pre-fabricated warped pavement slabs.
A seventh general aspect of the present invention provides a precision pre-fabricated warped pavement slab comprising: a pre-fabricated pavement slab formed of a hardenable, flowable material, wherein a top surface of the pavement slab is warped; and at least one edge of a cross section taken perpendicular to a longitudinal side is straight.
An eighth general aspect of the present invention provides a forming a plurality of prefabricated pavement slabs at a remote location; grading a subgrade; placing the prefabricated pavement slabs on the subgrade; and leveling at least one of the prefabricated pavement slabs with a flowable material.
The foregoing and other features of the invention will be apparent from the following more particular description of the embodiments of the invention.
The embodiments of this invention will be described in detail, with reference to the following figures, wherein like designations denote like elements, and wherein:
Although certain embodiments of the present invention will be shown and described in detail, it should be understood that various changes and modifications may be made without departing from the scope of the appended claims. The scope of the present invention will in no way be limited to the number of constituting components, the materials thereof, the shapes thereof, the relative arrangement thereof, etc. Although the drawings are intended to illustrate the present invention, the drawings are not necessarily drawn to scale.
Referring to the drawings,
The top surface 9 of the slab 10 is a roughened astroturf drag finish, while the sides 11a, 11b, 11c, 11d, and bottom surface 13 of the slab 10 have a substantially smooth finish (refer to
The slab 10 further includes a plurality of connectors 12 that may comprise transverse slippable connecting rods or dowels. The plurality of connectors 12 may be embedded within an end of the slab 10. In one embodiment, the connectors 12 are post tensioned interconnections, as known and used in the industry, wherein multiple slabs may be connected in compression. The connectors 12 are spaced approximately 1 ft. apart along the width W of the slab 10, and comprise steel rods, or other similar material conventionally known and used. Each connector 12 is of standard dimensions, approximately 14 inches in length and 1.25 inches in diameter. The slippable connectors 12 are mounted truly parallel to the longitudinal axis L of the slab 10 to allow adjacent slabs 10 to expand and contract without inducing unwanted damaging stresses in the slabs 10. The connectors 12 [are preferentially] can be mounted such that approximately half of the connector 12 is embedded within the pavement slab 10 and half of the connector 12 extends from the side of the slab 10.
The slab 10 further includes a plurality of inverted interconnection slots 14 formed within the bottom surface 13 of the slab 10 at a side 11c thereof. Each interconnection slot 14 is sized to accommodate the connectors 12 extending from the side of an adjacent slab 10, thereby forming an interconnection between adjacent slabs once the slot 14 is filled around the connectors 12 with a binder material.
In the alternative, the interconnection slots 14 may take the form of a “mouse hole” having a pair of cut-outs or holes 17 formed on both sides thereof, as illustrated in
As illustrated in
It has been previously noted that the connectors 12 are preferentially mounted as described above with approximately half of the connector 12 embedded in an adjacent slab while the other half is engaged and embedded in the interconnections slots 14 of slab 10. Alternatively, the same connector 12 may be preplaced on the subgrade, not shown, such that interconnections slots 14 in both slabs engage the connectors 12, such interconnection slots 14 being subsequently filled with binder material in the same manner described in the foregoing.
The slab 10 further includes a plurality, in this example three, channels 18 running longitudinally along the length L of the slab 10. The channels 18 formed within the bottom surface 13 of the slab 10 facilitate the even dispersement of a bedding material, such as bedding grout or concrete, a polymer foam material, or other similar material, to the underside of the slab 10. As shown in
As illustrated in
The slab 10 further includes a plurality of interconnection slots 24, shown in this example within a first side 11a of the slab 10 (
The slab 10 further includes a plurality of connectors 69 that may comprise longitudinal connectors, non-slippable connecting rods or dowels embedded within a second side 11b of slab 10 along the length L of the slab 10. As with the connectors 12, the connectors 69 may be post tensioned interconnections. The connectors 69 may be one-piece, where approximately half of the connector 69 is embedded within the pavement slab 10 and half of the connector 69 extends from the second side 11b of the slab 10. Alternatively, the connector 69 may be of a two-piece design comprising a first connector 54 and a second connector 56 as shown in
After the slab has been installed and the connectors are in their final location, a binder material, such as structural cement-based grout, a polymer foam, etc., is then injected into the interconnection slots 24, having the rods inserted therein, from the top surface 9 of the slab 10 via the ports 26. This aids in rigidly interconnecting adjacent slabs of the roadway and facilitates a relatively even load transfer between lanes.
The slab 10 further includes a top mat 32 and a bottom mat 34 (
A seal or gasket 36, comprising a compressible closed cell foam material, such as neoprene foam rubber or other similar material, is attached to the bottom surface 13 of the slab 10 around the perimeter of the slab 10, as illustrated in
In another embodiment, the gasket 36 can be made from a material selected of such a softness so that the slab 10 is held up a predetermined amount so as to create a design space for grout or other bedding material to be inserted. The softness of the selected material for the gasket 36 in this embodiment will conform so that the top surface 9 and bottom surface 13 of the slab 10 is held generally parallel to the surface of the prepared subgrade. This embodiment is useful when the subgrade, rather than compacted stone dust, is a dense graded base, as discussed below.
Optionally, additional sections of the gasket 36, having the same or similar width and thickness, may be applied to the bottom surface 13 of the slab 10 to form a plurality of individual chambers or cavities 38, as illustrated in
In an alternative embodiment (not shown) of the present invention, a different binder distribution system is employed. In lieu of gasket material 36, a geotech fabric, or the like, is used to hold the binder material. For example, two layers of a geotech fabric is attached to the slab 10 in various locations. The layers of geotech fabric may be additionally attached to each other in selective locations thereby forming pockets between the fabric layers which receive the pumped in grout. In addition, the bottom surface 13 of the slab 10 may be flat. The geotech fabric thus acts as a series of chambers to hold and distribute the grout, or similar binder material. In another embodiment, a single layer of geotech fabric is attached to the slab 10. Thus, the grout, or binder material, is pumped between the geotech fabric and the bottom surface 13 of the slab 10.
To install the slab 10, connectors 12 may first need to be installed along the transverse end of the existing slab 50, and connectors 69 may need to be installed along the longitudinal side of the existing slabs 50, to match interconnection slots 14 and 24, respectively. If so, a hole may be drilled within the existing slab 50, using carbide tipped drill bits, or other similar tools. Thereafter, the connector 12 or the connector 69 is inserted within each hole, along with a binder material, such as a cement-based or epoxy grout, polymer foam, etc., such that approximately one half of the connector 12 or the connector 69 extends therefrom, as illustrated in
Alternatively to installing connectors 12 and connectors 69 in the existing slab to mate with the interconnection slots 14 and 24 in the slab 10, the same connectors 12 and connectors 69 may be embedded in the slab 10 such that they extend from the slab 10 as described above. In this case, a vertical slot 70 is cut in the existing slabs 50 using a diamond blade concrete saw, or other similar tool, in locations corresponding to the extended connectors 12 and connectors 69 in slab 10 (refer to
In preparation for slab installation, the replacement area (the area in which the slab 10 will be placed) is cleaned of all excess material to provide a subbase or sub-grade approximately 25 mm below the theoretical bottom surface 13 of the slab 10. The subbase is graded with conventional grading equipment such as a grader, backhoe, skid steer loader, etc., and fully compacted with a vibratory roller or other similar device. The compacted subgrade is subsequently overlaid with approximately 30 mm of finely graded material such a stone dust that can be easily graded with the precision grading equipment described below.
The stone dust is then graded with a grading device, such as the Somero Super Grader™ (Somero Enterprises of Jafrey, N.H.), as illustrated in
For straight highways, where the cross-slope and the grade are constant, the rotating laser beam set as described above will serve to set multiple slabs. For both horizontally and vertically curved highways the rotating laser beam will have to be set to a distinct plane for each slab. This continuous adjustment may be done manually or automatically with software designed for that specific purpose. Alternatively, the screed may by controlled by other electronic means unique to the Somero Super Grader™.
Specific to the Somero Super Grader™, laser receivers 44, mounted on posts 46 above the screed 48, receive and follow the theoretical plane emitted from the transmitter 42 as the grading screed 48 is pulled over the replacement area leaving the stone dust approximately ¾″ high. After the first grading pass, the stone dust layer is damped with water and fully compacted with a vibratory roller or other similar device and a second, and final, grading (“shaving”) pass is made in which the subbase is brought to within 1/16th of an inch (or “Super-Graded”) of the required theoretical plane. The stone dust layer is dampened with water, as needed for the subsequent grouting process, in final preparation for installation of the slab 10.
In an alternative embodiment, the layer of finely grade material such as stone dust is omitted. In lieu of the stone dust, a dense graded base is placed in two lifts. The first lift is placed about 1″ lower than theoretical elevation. It is then wetted and rolled such that its final average elevation is slightly lower than the required final elevation of the bottom surface 13 of the slab 10. The second lift is super graded in a similar fashion to an elevation slightly higher (e.g., ¼″) than theoretical elevation and wetted and rolled as required in final preparation for installation of the slab 10. The second lift of dense graded base typically cannot be supergraded (“shaved”) after is has been wetted and rolled because unlike the stone dust the dense graded base has variable size and larger stone that would get pulled up from the subgrade. Thus, when dense graded base is used as a subbase material, the finished surface is more apt to be slightly rougher in that there will exist larger stone that sticks up above the surface of the rest of the field of dense graded base. It is because of these projecting stones, that the embodiment for the gasket 36 material discussed above that is not fully compressible is used. The non-fully compressible gasket 36 is able to mold around and conform to the projecting stones in the final graded dense graded base without changing the final average elevation of the placed slab 10.
The slab 10 is placed within the replacement area such that the slab 10 contacts the subbase uniformly so as not to disrupt the subbase or damage the slab 10. During placement, the slab 10 is lowered vertically to the exact location required to match the adjacent existing slabs 50. Care is taken to insure the interconnection slots 14 and 24, within the sides and end (if an adjacent slab is present at the end of the slab 10) of the slab 10 are lowered over the connectors 12 and connectors 69 extending from the ends and sides of the adjacent slabs 50 respectively. In the case where connectors 12 and connectors 69 extend from the slab 10, the slab 10 is also lowered vertically and carefully to insure the connectors 12 and connectors 69 are set within the slots 70 of the adjacent existing slabs 50. At this time, the slab 10 should be within 6 +/− mm of the theoretical plane emitted from the rotating laser transmitter 42. In the event the surface 9 of the slab 10 is out of the required tolerance it is planed with a conventional diamond grinder until it is brought within tolerance.
The interconnection slots 14, 24 or 70, as the case may be are filled from the top surface 9 of the slab 10 with a binder material such as structural grout, or in the alternative, a polymer foam material, thereby fastening the slab 10 to the connectors 12, 54, 56, 69 or the slot 70 of the adjacent existing slabs 50. In particular, the binder material is injected under pressure into a first port 16, 26 of the interconnection slots 14, 24, respectively, until the binder material begins to exit the port 16, 26 at the other end of the interconnection slot 14, 24. It is desirable for the binder material within the slots 14, 24 to reach sufficient strength to transfer load from one slab to the other before opening the slab 10 to traffic.
The chamber(s) 38 formed by the gasket 36 on the bottom surface 13 of the slab 10 is/are then injected from the top surface 9 of the slab 10 with bedding material, such as grout including cement, water and fly ash, or in the alternative with a polymer foam material. In particular, starting from the lowest or downhill region, bedding material is injected into the port 20 at one end of the channel 18 until the bedding material begins to exit the port 20 at the other end of the channel 18. The bedding material is injected into the channels 18 to ensure that all voids existing between the bottom surface 13 of the slab 10 and the subbase, regardless of size, are filled. The slab 10 should be monitored during injection of the bedding material to ensure the slab 10 is not vertically displaced due to the upward pressure created thereunder. It is desirable for the bedding material under the slab 10 to reach a minimum strength of approximately 10.3 MPa before opening the slab 10 to traffic.
It should be noted that due to the precision of the Super Graded subbase, the channels 18 may not need to be filled prior to exposure of the slab 10 to traffic. Rather, the channels 18 may be filled within 24-48 hours following installation of the slab 10 without damaging the slab 10 or the subbase. In other words, if required, vehicular traffic can be allowed on the slabs 10 immediately after the placement of the slabs 10. This is particularly useful due to time constraints.
A warped slab is defined as a slab that has a warped surface. A slab being a body of uniform thickness in which the sides are substantially perpendicular to both the top and bottom surfaces. A warped surface being a surface in which all the points of the surface are not in a single plane. That is, the slab is not entirely planar, but warped. For example, with a rectangular-shaped warped slab, three of the four corners of the slab could be in a single plane. The fourth corner conversely would not reside in this same single plane. This fourth corner would be either “higher” or “lower” in relationship to the plane in which the other three corners reside. With the warped slab, typically both the top and bottom surfaces are parallel and warped. Thus, the warped slabs top and bottom surfaces will both match and be substantially parallel to the surface of the subgrade on which the warped slab is placed. A warped slab is further defined wherein all the edges are straight, wherein an edge is the intersecting line between any side and either the top or bottom surface of the slab. Further, with a warped slab, when any cross section is taken that is perpendicular to a longitudinal side, the resultant edges (i.e., the lines at the top and bottom surface of the cross-sectional “cut”) will likewise be straight lines. Conversely, if a diagonal (i.e., non-perpendicular) cross section is taken of the warped slab, the resultant edges (i.e., the lines at the top and bottom surface of the cross-sectional “cut”) will not be straight, but non-linear.
The use of a warped slab in roadway construction is typically called for when the cross-sectional slope of a road lane changes over the longitudinal length of the roadway slab. Similarly, a warped slab in roadway construction could also be used when the roadway lane is both curved over the longitudinal length of the roadway slab and has a change in elevation over the longitudinal length (i.e., profile change) of the roadway slab. Prefabricated warped pavement slabs could be used, for example, both over subgrade in a roadway as well as in an elevated condition such as bridge, viaduct, or parking garage construction.
The present invention is able to make precision pre-fabricated warped pavement slabs with precision tolerances throughout the whole plan area of the slab. The device is able to thus make prefabricated pavement slabs either in a flat slab configuration or a warped slab having a total warp in the range from 3-4 mm to approximately 3 inches. Although the shape, in plan, of the warped slab can be rectangular, other non-rectangular shapes are readily attainable with the present invention. Another advantage of the present invention is the ability to construct a pre-fabricated warped pavement slab wherein the warp in the slab matches precisely and uniformly throughout the whole area of the slab a predetermined warp required for the specific roadway section being built, as well as, precisely matching the warp of the entire subgrade in the location where the slab will be placed. Another advantage of the present invention is the ability to quickly install prefabricated pavement slabs in their final location and to allow vehicular traffic use the installed pavement shortly after the installation.
In order to create a pre-fabricated warped pavement slab 100 a portion of the formwork must be placed out of the plane of the remaining planar portion of the formwork. This is done by lifting, or lowering, the corner, or area of the formwork which must be moved out of plane from the remaining planar portion of the formwork. The formwork for making the pre-fabricated warped pavement slabs 100 have an advantage of being at a remote location. That is the formwork can be adjacent, or on the applicable construction project, or at a remote location wherein additional quality controls and assurances can more readily take place.
In
Beneath the plurality of form sections 170 is equipment which, in part, comprise the device for adjusting 120 the warp of the form system 110.
A perspective view of a typical jacking, or floating, beam 140 is depicted in
It should be apparent to one skilled in the art that the form system 110, while able to make warped pavement slabs 100, can be used just as readily make a flat (i.e., non-warped) pavement slab 10. Similarly, the various devices, appurtenances, methods, and pavement systems disclosed above for use with a flat pavement slab 10, can readily by applied as well in making and installing the warped pavement slab 100.
While this invention has been described in conjunction with the specific embodiments outlined above, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art. Accordingly, the embodiments of the invention as set forth above are intended to be illustrative, not limiting. Various changes may be made without departing from the spirit and scope of the invention as defined in the following claims.
Patent | Priority | Assignee | Title |
10006174, | Aug 19 2016 | JERSEY PRECAST CORPORATION, INC | Pavement slab |
Patent | Priority | Assignee | Title |
1252093, | |||
1498651, | |||
2616148, | |||
3599542, | |||
4442995, | Jan 15 1979 | Machine for concrete molding | |
4679763, | Aug 22 1985 | BANK OF AMERICA, N A | Concrete form having adjustable curvature and method for producing same |
4742986, | Nov 07 1985 | Apparatus for constructing concrete buildings | |
4826639, | Jan 21 1986 | TERRE ARMEE INTERANTIONALE | Moulding process and apparatus for making arch-shaped concrete structures |
6354561, | Jul 11 1996 | Adjustable casting mould, and device for adjusting the mould surface thereof | |
862418, | |||
20010018006, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Jun 25 2000 | SMITH, PETER J | FORT MILLER CO , INC | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 016169 | /0315 | |
Dec 23 2004 | Fort Miller Co., Inc. | (assignment on the face of the patent) | / |
Date | Maintenance Fee Events |
May 31 2012 | M2551: Payment of Maintenance Fee, 4th Yr, Small Entity. |
May 20 2016 | M2552: Payment of Maintenance Fee, 8th Yr, Small Entity. |
Jun 01 2020 | M2553: Payment of Maintenance Fee, 12th Yr, Small Entity. |
Date | Maintenance Schedule |
Dec 23 2011 | 4 years fee payment window open |
Jun 23 2012 | 6 months grace period start (w surcharge) |
Dec 23 2012 | patent expiry (for year 4) |
Dec 23 2014 | 2 years to revive unintentionally abandoned end. (for year 4) |
Dec 23 2015 | 8 years fee payment window open |
Jun 23 2016 | 6 months grace period start (w surcharge) |
Dec 23 2016 | patent expiry (for year 8) |
Dec 23 2018 | 2 years to revive unintentionally abandoned end. (for year 8) |
Dec 23 2019 | 12 years fee payment window open |
Jun 23 2020 | 6 months grace period start (w surcharge) |
Dec 23 2020 | patent expiry (for year 12) |
Dec 23 2022 | 2 years to revive unintentionally abandoned end. (for year 12) |