A floating, offshore drilling and/or production platform is equipped with a rail-mounted transport system that can be positioned at a plurality of selected positions over the well bay of the vessel. The transport system can move a drilling riser with a drilling riser tensioner system and a blowout preventer from one drilling location to another without removing them from the well bay of the vessel. Using the transport system, the drilling riser is lifted just clear of a first well head and positioned over an adjacent, second well head using guidelines. The transport system may then move the upper end of the drilling riser (together with its attached tensioner and BOP) to a second drilling location. A dummy wellhead may be provided on the seafloor in order to secure the lower end of the drilling riser without removing it from the sea while production risers are being installed.
|
1. An offshore drilling vessel comprising:
a deck support structure;
a deck supported by the deck support structure and having an upper surface and an under surface;
a through opening in the deck from the upper surface to the under surface;
a transporter adapted for translational movement within the through opening along a central column of an array of well slots from a first drilling location to a second drilling location, and
wherein side columns are provided along the central column, said side columns configured for installation of one or more production risers.
2. The offshore drilling vessel according to
3. The offshore drilling vessel according to
4. The offshore drilling vessel according to
5. The offshore drilling vessel according to
6. The offshore drilling vessel recited in
7. The offshore drilling vessel according to
a plurality of riser tensioners above the well slots in the array of well slots, each tensioner configured for mounting an associated production riser.
8. The offshore drilling vessel according to
an adapter frame within the transporter moveable from a first position wherein a load on the adapter frame is borne by the transporter to a second position wherein a load on the adapter frame is substantially borne by the deck support structure and not by the transporter.
9. The offshore drilling vessel recited in
10. The offshore drilling vessel recited in
11. The offshore drilling vessel recited in
12. The offshore drilling vessel recited in
13. The offshore drilling vessel recited in
14. The offshore drilling vessel recited in
15. The offshore drilling vessel recited in
17. The offshore drilling vessel recited in
18. The offshore drilling vessel recited in
19. The offshore drilling vessel recited in
20. The offshore drilling vessel recited in
a pair of openings in the transporter;
at least two guide lines each passing through one of the openings in the transporter;
at least two winches each connected to the deck support structure and engaged with one of the at least two guide lines; and,
a pair of sheaves each mounted on the adapter frame and in contact with one of the at least two guide lines.
21. The offshore drilling vessel recited in
22. A drilling riser transport assembly for an offshore drilling vessel recited in
a transport trolley adapted for translational movement on the deck support structure; and,
an adapter frame attached to the transport trolley and moveable from a first position wherein a drilling riser connected to the adapter frame is supported by the transport trolley to a second position wherein the drilling riser is supported by the deck support structure and not by the transport trolley.
|
This application is a continuation of U.S. application Ser. No. 14/919,486 filed Oct. 21, 2015, which is a continuation of U.S. application Ser. No. 13/646,277 filed on Oct. 5, 2012, which claims the benefit of U.S. Provisional Application No. 61/543,663, filed on Oct. 5, 2011, and U.S. Provisional Application No. 61/606,031, filed on Mar. 2, 2012, and U.S. Provisional Application No. 61/610,805, filed on Mar. 14, 2012. Each of these five applications is hereby incorporated by reference in its entirety.
Not Applicable
1. Field of the Invention
This invention relates to offshore drilling and production platforms. More particularly, it relates to a method and apparatus for drilling a plurality of wells at a single platform (or vessel) location and installing production risers on those wells.
2. Description of the Related Art Including Information Disclosed Under 37 CFR 1.97 and 1.98
Both tension leg platforms (TLP's) and semi-submersible floating vessels (“semis”) can be used for offshore drilling and production operations.
An offshore drilling vessel (TLP) is a vertically moored floating structure typically used for the offshore production of oil and/or gas, and is particularly suited for water depths greater than about 1000 ft.
The platform is permanently moored by tethers or tendons grouped at each of the structure's corners. A group of tethers is called a tension leg. The tethers have relatively high axial stiffness (low elasticity) such that virtually all vertical motion of the platform is eliminated. This allows the platform to have the production wellheads on deck (connected directly to the subsea wells by rigid risers), instead of on the seafloor. This feature enables less expensive well completions and allows better control over the production from the oil or gas reservoir.
A semi-submersible is a particular type of floating vessel that is supported primarily on large pontoon-like structures that are submerged below the sea surface. The operating decks are elevated perhaps 100 or more feet above the pontoons on large steel columns. This design has the advantage of submerging most of the area of components in contact with the sea thereby minimizing loading from wind, waves and currents. Semi-submersibles can operate in a wide range of water depths, including deep water. The unit may stay on location using dynamic positioning (DP) and/or be anchored by means of catenary mooring lines terminating in piles or anchors in the seafloor. Semi-submersibles can be used for drilling, workover operations, and production platforms, depending on the equipment with which they are equipped. When fitted with a drilling package, they are typically called semi-submersible drilling rigs.
The DeepDraftSemi® vessel offered by SBM Offshore, Inc. (Houston, Tex.) is a semi-submersible fitted with oil and gas production facilities that is suitable for use in ultra-deep water conditions. The unit is designed to optimize vessel motions to accommodate steel catenary risers (SCRs).
A floating, offshore drilling and/or production platform is equipped with a rail-mounted transport system that can be positioned at a plurality of selected positions over the well bay of the vessel. The transport system can move a drilling riser with a drilling riser tensioner system and a blowout preventer from one drilling location to another without removing them from the well bay of the vessel. Using the transport system, the drilling riser is lifted just clear of a first well head and positioned over an adjacent, second well head using guidelines. The transport system may then move the upper end of the drilling riser (together with its attached tensioner and BOP) to a second drilling location. A dummy wellhead may be provided on the seafloor in order to secure the lower end of the drilling riser without removing it from the sea while production risers are being installed.
The invention may best be understood by reference to one particular preferred embodiment whose apparatus is illustrated in
The system shown is intended for use on a well pattern which is essentially rectangular in shape, but it should be understood that similar methodology could be adapted to well patterns of a more square shape or other patterns.
One particular feature of the system is a transfer trolley, which is suspended from the lower deck (the production deck) of the floating platform. The transfer trolley is set to run down the length of the well pattern. The position of the transfer trolley is held side to side by fixed rails, or similar, which may form part of the deck structure. The end-to-end position of the transfer trolley may be shifted using a rack-and-pinion arrangement with the pinion(s) turned by hydraulic motors or the like. The end-to-end position of the transfer trolley may be controlled by other means—for example by a pair of opposing winches used to translate the transfer trolley.
The transfer trolley may be used to transport the assembled drilling riser together with an associated tensioner and blowout preventer (BOP) between well bay positions.
The production deck (the lower deck) of the floating structure may contain discrete (separate) tensioners 42 for the near-vertical production risers. These tensioners may be arranged in a regular geometric pattern, as shown in
Referring in particular to
As shown in
Also shown in the top and side views of
As illustrated in
In
Extending adapter frame 66 results in lifting the drilling riser assembly sufficiently to clear the wellhead on the seafloor to which is was connected. This permits the drilling riser assembly to be moved horizontally within the well bay without disconnecting either the drilling BOP 26 or the drilling riser tensioner system 30. Moreover, the drilling riser itself may remain in the sea. In certain embodiments, a dummy wellhead may be provided on the seafloor for landing and securing the lower end of the drilling riser while production risers are run. This can help to prevent collisions between the risers.
Specific design parameters for one particular preferred embodiment of a drilling riser transport system according to the invention are:
As shown in the sequence illustrated in
Although particular embodiments of the present invention have been shown and described, they are not intended to limit what this patent covers. One skilled in the art will understand that various changes and modifications may be made without departing from the scope of the present invention as literally and equivalently covered by the following claims.
Jordan, Travis Randall, Kipp, Robert M.
Patent | Priority | Assignee | Title |
10428599, | Sep 07 2016 | FRONTIER DEEPWATER APPRAISAL SOLUTIONS LLC | Floating oil and gas facility with a movable wellbay assembly |
10865608, | Sep 07 2016 | FRONTIER DEEPWATER APPRAISAL SOLUTIONS LLC | Movable wellbay assembly |
9988848, | Oct 05 2011 | SINGLE BUOY MOORINGS, INC | Method and apparatus for drilling multiple subsea wells from an offshore platform at a single site |
Patent | Priority | Assignee | Title |
3474629, | |||
4007782, | Mar 18 1974 | Finn Tveten & Co. A/S; A/S Akers Mek. Verksted | Parking device for blowout preventer |
4108318, | Jun 07 1974 | Sedco, Inc. of Dallas, Texas | Apparatus for offshore handling and running of a BOP stack |
4324077, | Oct 26 1979 | Lee C. Moore Corporation | Method of moving a drilling rig long and short distances |
4367796, | Nov 21 1980 | Global Marine, Inc. | Blowout preventer and guideline handling |
4557332, | Apr 09 1984 | Shell Offshore Inc. | Drilling riser locking apparatus and method |
4716972, | Jun 15 1982 | Masa-Yards Oy | Floating drilling platform |
4899682, | Dec 03 1986 | Schlumberger Technology Corporation | Catamaran-type semisubmersible drilling vessel for offshore drilling |
5150987, | May 02 1991 | Conoco Inc. | Method for installing riser/tendon for heave-restrained platform |
5492436, | Apr 14 1994 | Pool Company | Apparatus and method for moving rig structures |
6691784, | Aug 31 1999 | Maritime Hydraulics AS | Riser tensioning system |
7451821, | Oct 29 2003 | Saudi Arabian Oil Company | Blow out preventer transfer platform |
7628225, | Apr 02 2007 | Kellogg Brown & Root LLC | Drilling device |
8522880, | Apr 29 2008 | ITREC B V | Floating offshore structure for hydrocarbon production |
9051783, | Nov 17 2008 | SAIPEM S P A | Vessel for operating on underwater wells and working methods of said vessel |
9238943, | Oct 05 2011 | SINGLE BUOY MOORINGS, INC | Method and apparatus for drilling multiple subsea wells from an offshore platform at a single site |
9341025, | Oct 18 2011 | TOTALENERGIES ONETECH PREVIOUSLY TOTALENERGIES ONE TECH ; TOTALENERGIES ONETECH | Floating offshore facility and a method for drilling a well |
20020074125, | |||
20040134661, | |||
20090025937, | |||
20100147528, | |||
20120018166, | |||
20130195559, | |||
20160145943, | |||
WO9932352, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Nov 06 2012 | JORDAN, TRAVIS RANDALL | Seahorse Equipment Corp | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 041144 | /0657 | |
Nov 06 2012 | KIPP, ROBERT M | Seahorse Equipment Corp | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 041144 | /0657 | |
Nov 06 2012 | JORDAN, TRAVIS RANDALL | Seahorse Equipment Corp | CORRECTIVE ASSIGNMENT TO CORRECT THE ATTORNEY DOCKET NUMBER PREVIOUSLY RECORDED ON REEL 041144 FRAME 0657 ASSIGNOR S HEREBY CONFIRMS THE ASSIGNMENT | 042201 | /0039 | |
Nov 06 2012 | KIPP, ROBERT M | Seahorse Equipment Corp | CORRECTIVE ASSIGNMENT TO CORRECT THE ATTORNEY DOCKET NUMBER PREVIOUSLY RECORDED ON REEL 041144 FRAME 0657 ASSIGNOR S HEREBY CONFIRMS THE ASSIGNMENT | 042201 | /0039 | |
Sep 09 2016 | Seahorse Equipment Corp | (assignment on the face of the patent) | / | |||
Jul 07 2017 | Seahorse Equipment Corporation | SINGLE BUOY MOORINGS, INC | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 043272 | /0464 |
Date | Maintenance Fee Events |
Nov 24 2020 | M1551: Payment of Maintenance Fee, 4th Year, Large Entity. |
Nov 21 2024 | M1552: Payment of Maintenance Fee, 8th Year, Large Entity. |
Date | Maintenance Schedule |
Jun 13 2020 | 4 years fee payment window open |
Dec 13 2020 | 6 months grace period start (w surcharge) |
Jun 13 2021 | patent expiry (for year 4) |
Jun 13 2023 | 2 years to revive unintentionally abandoned end. (for year 4) |
Jun 13 2024 | 8 years fee payment window open |
Dec 13 2024 | 6 months grace period start (w surcharge) |
Jun 13 2025 | patent expiry (for year 8) |
Jun 13 2027 | 2 years to revive unintentionally abandoned end. (for year 8) |
Jun 13 2028 | 12 years fee payment window open |
Dec 13 2028 | 6 months grace period start (w surcharge) |
Jun 13 2029 | patent expiry (for year 12) |
Jun 13 2031 | 2 years to revive unintentionally abandoned end. (for year 12) |