system for repairing worn surfaces of steam turbine components and especially high pressure turbine rotors, are disclosed. These systems include depositing a first layer of weld metal on a worn surface of the component, whereby a heat-affected zone is created. A second layer of weld metal is then deposited over the first layer using a greater amount of heat to temper at least a portion of the heat-affected zone produced by the first layer. The preferred embodiments include the use of gas tungsten arc welding for providing fine-grain size and more creep resistance, especially in the weld and heat-affected zone. The resulting build-up can be machined, for example into a blade fastening to produce a component having properties equal to or better than the base-metal alloy. The invention also provides a longer lasting turbine system, including rotors which have serrated steeples that are more resistant to failure.
|
1. In a steam turbine system of the type having a ferrous steam turbine component, said component having a worn surface thereon, the improvement comprising:
(a) a first layer of weld metal deposited on said worn surface, said deposition of said first layer producing a heat-affected zone in said component; and (b) a second layer of weld metal deposited to said first layer, said deposition of said second layer tempering at least a portion of said heat-affected zone in said component, wherein said turbine component comprises about 1.05% to 1.35% by weight Cr, about 1.00% to about 1.30% by weight Mo, and about 0.21% to 0.29% by weight V.
3. The system of
4. The system of
5. The system of
6. The system of claim 1 5 wherein at least one of said steeple steeples has a higher creep resistance than that of the ferrous steam turbine component.
0. 7. The system of % C.
|
This is
The novel methods of repairing worn surfaces of ferrous turbine components of this invention include providing a ferrous turbine component 20, 40, or 50 having Cr, Mo and V alloying ingredients. These turbine components 20, 40, or 50 include worn surfaces, however it is expected that new components can be manufactured using the methods disclosed herein. The repairing procedure includes depositing a first layer of weld metal the worn surface of the component thereby producing a heat-affected zone in that component. The procedure next deposits a second layer of weld metal on top of the first layer. This second layer is deposited with a greater amount of heat than the depositing of the first layer for tempering at least a portion of the heat affected zone produced by the first depositing step. As used herein, the term "tempering" refers to the process wherein the heat-affected zone of the base metal is re-heated and then cooled to relieve internal stress and reduce its hardness.
By carefully controlling the weld parameters for the first to five layers of weld build-up, problems associated with the heat-affected zone and resulting coarse grain structure of the base metal can be overcome. More specifically, using a gas tungsten arc weld procedure, the first layer is deposited using about 40 to 60 amperes, more preferably about 60 to 140 amperes, and most preferably, about 80 to 120 amperes of direct current. The initial layer is welded at a relatively low amperage to create as small a heat-affected zone as possible. Next, the second layer of weld metal is deposited using about 50 to 200 amperes, more preferably 75 to 175 amperes, and most preferably about 100 to 150 amperes of direct current. Alternatively, alternating current could be employed less advantageously.
The higher amperage associated with the application of the second layer of weldment has the effect of "heat treating" or tempering the relatively brittle heat-affected zone in the turbine component. Following this second layer, the third and fourth layers preferably are applied using the same amount of current as used for applying the first layer. The fifth and subsequent layers can be applied using a higher current, since it will have less of an effect on the base metal.
It must be understood that the above current preferences are ideally suited for a gas tungsten arc welding procedure using a wire size of about 0.045 inches, a 50% argon-50% helium gas mixture, and a ⅛ or 3/32 tungsten size. It is expected that the tempering effect caused by the depositing of the second layer could be accomplished by varying these and other parameters to obtain the same effect. For example, if a smaller wire size for the deposited alloy were used for depositing the second layer of weld metal, the amperage could remain about at the same setting as the setting used for depositing the first layer. This, and other techniques, are well within the knowledge of those in the welding art, and are mere variations of the principal teachings of this invention.
The ferrous alloys preferably used in this invention to repair the Cv-Mo-V components of steam turbines are selected to include one or more of the following elements: Cr, Mo, Si, C, Mn, V, Nb, and N. In a more preferred embodiment, the ferrous alloy applied to the worn component is selected to comprise about 7.0 to 11.0 weight percent Cr and about 0.1 to 3.0 weight percent Mo. One specified preferred ferrous alloy composition range consists essentially of about 0.04 to 0.22 weight percent C, 0.15 to 1.0 weight percent Mn, 0.15 to 1.0 weight percent Si, 0.0 to 0.02 weight percent P, 0.0 to 0.016 weight percent S, 0.0 to 0.8 weight percent Ni, 4.00 to 19.0 weight percent Cr, 0.43 to 2.1 weight percent Mo, 0.09 to 0.5 weight percent V, 0.03 to 0.20 weight percent Nb, 0.0 to 0.08 weight percent Al, 0.0 to 0.20 weight percent Cu, 0.005 to 0.06 weight percent N and the balance being Fe. However, the most preferred a ferrous alloy consists essentially of 0.08 to 0.11 weight percent C, 0.30 to 0.50 weight percent Mn, 0.30 to 0.50 weight percent Si, 0.00 to 0.10 weight percent P, 0.00 to 0.008 weight percent S, 0.00 to 0.40 weight percent Ni, 8.00 to 9.50 weight percent Cr, 0.85 to 1.05 weight percent Mo, 0.18 to 0.25 weight percent V, 0.06 to 0.10 weight percent Nb, 0.00 to 0.04 weight percent Al, 0.00 to 0.10 weight percent Cu, 0.01 to 0.03 weight percent N and the balance being Fe.
In further accordance to these novel methods, the depositing step can consist of welding the ferrous alloy to the worn surface of the turbine component. This welding step preferably is accomplished by any one of gas tungsten arc welding, plasma-arc welding, electron beam welding, laser-beam welding and gas metal arc welding. It is expected that other welding procedures may be used to apply the novel alloys of this invention, however, it is important that the welding procedure employed minimize the heat-affected-zone in the base metal so as to avoid unnecessary defects.
The most preferred procedure employed thus far comprises gas tungsten arc welding (GTAW) the preferred ferrous alloys to a machined or ground turbine component. GTAW is preferred because its multiple bead depositions exhibit exceptionally fine-grain size in the weld and heat-affected zone. This fine-grain size translates into exceptional low and high cycle fatigue, tensile, impact and creep-to-rupture properties.
In accordance with the preferred gas tungsten arc welding procedures of this invention, the steam turbine component 20, 40, or 50 is preheated to at least about 177°C C. prior to the welding step. Side plates may be employed for "360°C" welding applications on discs and rotors. As used herein, a "360°C" repair refers to a procedure wherein weld metal is deposited continuously about the circumference of a turbine component, such as a rotor or disc, until a sufficient height is reached whereupon the individual steeples of the rotor are machined, or the disc is machined down to service tolerances. The side plates preferably are manufactured from Cr-Mo-V rotor steel or copper, and can be water cooled to further reduce welding side effects.
For a 360°C steeple weld build up as described in
During a preferred (GTAW) welding repair of a single steeple repair, a first bead is welded transversely across the rotor on the machined or otherwise prepared surface. Next, a second bead is welded transversely across the rotor on the prepared surface, and spaced apart from the first bead. The third and fourth weld beads are similarly disposed and spaced apart, if room is available. Using this intermittent welding procedure permits the immediate area of base metal underneath the weld to slowly cool prior to the next adjoining welding application. Accordingly, the brittleness associated with a weld-created, heat affected zone is minimized.
The turbine rotor 20 of
Generally the steam turbine rotors, discs and blades of this invention are manufactured from low alloy steel, commonly containing less than 6% alloying elements. Of particular importance to these applications is the Cr-Mo-V alloy, A 470, Class 8, and its modified versions. One most preferred composition includes 0.27-0.34% by weight C, 0.70-1.0% by weight Mn, 0.012% by weight P and S (max), 0.20-0.35% by weight Si, 0.50% by weight Ni (max), 1.05-1.35% by weight Cr, 1.00-1.30% by weight Mo 0.21-0.29% by weight V, 0.15% be weight Cu (max), 0.010% by weight Al (max); 0.0015% by weight Sb(max), 0.015% by weight Sn (max), and 0.020% by weight As (max). Other forging alloys which can be used for making steam turbine components for high pressure service may also be repaired through the processes of this invention, such as those containing varying amounts of Ni, Co, Cr and other alloying ingredients.
When a used turbine component, such as rotor 20, 40, and 50 are employed, the highly stressed, individual steeples 44 are preferably mechanically removed. As used herein, "mechanically removing" refers to any of the known procedures for removing metal, including but not limited to, grinding, machining, electric arc gouging, and other methods known to those in the metallurgy arts. As in the case of
As generally described in
In preparation for the preferred gas tungsten arc welding procedure of this invention, the surfaces to be welded are preferably conditioned to bright metal. More preferably, the base metal surfaces are cleaned for a distance of about 2 inches from the weld area with denatured alcohol, acetone, methyl chloroform, or solvent cleaner. It is further noted that if methyl chloroform is applied, it should be followed with an alcohol, acetone or solvent wash. It is also advised that the base metal surface to be welded be inspected using non-destructive testing procedures, and that at least one sixteenth inch of additional metal be removed beyond the deepest crack or fatigued area found.
In accordance with the preferred GTAW procedure of this invention, the following welding parameters have been deemed useful:
TABLE II | |||
Remainder | |||
Parameter | Layer 1,3,4 | Layer 2 | of Weld |
Nature of Current | Pulsed 60% | Pulsed 60% | Straight |
(no pulse) | |||
Amperage-DCSP | 85-120 | 100-150 | 280 |
Voltage | 8.5-9.0 | 9.0-10 | 11-13 |
Surface Speed | 4.0 | 3.0 | 4.5-8.0 |
(Linear), Inch | |||
Frequency of Pulse | 3 cycles/sec | 3 cycles/sec | None |
Type of Travel | OSC | OSC | Straight |
Osc. Amplitude | .22 | .22 | 0 |
Wire Feed Speed, | 5-25 | 5-20 | 50 |
inches per min. | |||
Tungsten Size, | 1 or 3/32 | 1 or 3/32 | 1 |
2% Thorium, inch | |||
dia | |||
Tungsten Stickout, | 1-1 | 1-1 | 1-1 |
inch | |||
Wire Size, | .045 | .045 | .045 |
inch dia | |||
Primary Shield, | 50% + 50% | 50% + 50% | 50% + 50% |
Argon-Helium | |||
Trail Shield, | 100% | 100% | 100% |
Argon | |||
Bead Overlap | 50% | 50% | 50% |
As described in
During the welding procedure, the interpass temperature of the base metal preferably should be below 300°C C., preferably below 250°C C., and most preferably below 204°C C. Immediately after welding, the welded turbine component 20, 40, or 50 and its weldment 12, 42, or 54 should be maintained at a temperature of about 149°C C. to about 260°C C., preferably about 176°C C. to about 204°C C. After this post-heat maintenance schedule, the welded turbine component 20, 40, or 50 can be given a post-weld heat treatment above 500°C C., preferably above 600°C C., and more preferably about 663°C C. The post-weld heat treatment temperature should be selected to minimize weld stresses, provide sufficient "tempering back" of the weld and heat affected zone hardness, and if necessary, prevent "over tempering" of the unaffected base metal to obtain the required weld strength. The preferred rotor repair techniques of this invention generally include a port-weld heat treatment locally at the repair weld area. This local stress relief consists of heating the entire repair area and also axially along the rotor to meet any preselected axial and radial temperature gradient.
Following the post-weld heat treatment of the welded area, the turbine components 20, 40 and 50 repaired by the above-mentioned procedures are blast cleaned and provided with a nondestructive examination, for example, magnetic particle, dye penetrant or ultrasonic testing. In addition, mechanical testing is conducted by determining the hardness of the weld deposit and by tensile testing metal coupons that were fabricated during the same welding operation. The turbine component is then ready for final dimensional checks and a finishing machining operation, i.e. to produce individual serrations 14.
From the foregoing, it can be realized that this invention provides improved procedures for repairing ferrous steam turbine components. The welding methods, alloys, and heat treatment schedules provide a repaired surface exhibiting improved high temperature properties which may include, for example, better creep and fatigue properties than the base metal of such components. Although various embodiments have been illustrated, this was for the purpose of describing, and not limiting the invention. Various modifications, which will become apparent to one skilled in the art, are within the scope of this invention described in the attached claims.
Clark, Robert E., Amos, Dennis R.
Patent | Priority | Assignee | Title |
6426152, | Dec 14 2000 | General Electric Company | Salvaged castings and methods of salvaging castings with defective cast cooling bumps |
6802122, | May 26 2001 | Rolls-Royce plc | Method of manufacturing an article |
6844520, | Sep 26 2002 | General Electric Company | Methods for fabricating gas turbine engine combustors |
7281901, | Dec 29 2004 | Caterpillar Inc. | Free-form welded power system component |
7316057, | Oct 08 2004 | SIEMENS ENERGY, INC | Method of manufacturing a rotating apparatus disk |
7568609, | Nov 21 2003 | MITSUBISHI HEAVY INDUSTRIES AERO ENGINES, LTD | Welding method |
7591057, | Apr 12 2005 | General Electric Company | Method of repairing spline and seal teeth of a mated component |
7687151, | Apr 12 2005 | General Electric Company | Overlay for repairing spline and seal teeth of a mated component |
7722330, | Oct 08 2004 | SIEMENS ENERGY, INC | Rotating apparatus disk |
8266800, | Sep 10 2003 | SIEMENS ENERGY, INC | Repair of nickel-based alloy turbine disk |
8367964, | Aug 06 2008 | RAYTHEON TECHNOLOGIES CORPORATION | Repair methods involving conductive heat resistance welding |
8408011, | Apr 30 2009 | Pratt & Whitney Canada Corp. | Structural reinforcement strut for gas turbine case |
8561415, | Apr 30 2009 | Pratt & Whitney Canada Corp. | Method of making a structural reinforcement strut for a turbine exhaust case of a gas turbine engine |
8959767, | Nov 21 2012 | RAYTHEON TECHNOLOGIES CORPORATION | Method of extending life of rotating parts |
9126287, | Mar 12 2012 | SIEMENS ENERGY, INC | Advanced pass progression for build-up welding |
9656354, | Jan 11 2011 | Rolls-Royce Deutschland Ltd & Co KG | Method for repairing compressor or turbine drums |
Patent | Priority | Assignee | Title |
3564689, | |||
3925634, | |||
4049186, | Oct 20 1976 | General Electric Company | Process for reducing stress corrosion in a weld by applying an overlay weld |
4066832, | Apr 11 1975 | Bristol-Myers Company | 0-2-Isocephem-4-carboxylic acid derivatives as antibacterial agents |
4196335, | Mar 26 1976 | Sumitomo Metal Industries, Ltd. | Submerged arc welding process |
4213025, | Jul 02 1976 | BBC Brown, Boveri & Company, Limited | Apparatus for connecting metallic parts by means of arc fusion welding |
4218604, | Apr 19 1978 | Hitachi, Ltd. | Method for welding of austenitic stainless steel piping |
4219717, | Jul 02 1976 | BBC Brown, Boveri & Company Limited | Method of connecting metallic parts by means of arc fusion welding |
4223197, | Apr 18 1978 | Hitachi, Ltd. | Method of cooling weld in steel piping and apparatus therefor |
4234119, | Aug 12 1977 | Hitachi, Ltd. | Method of making a structure immune against stress corrosion cracking |
4247037, | Jul 11 1978 | Hitachi, Ltd. | Method for welding tubular members of stainless steel |
4273512, | Jul 11 1978 | MTU Motoren-und Turbinen-Union Munchen GmbH | Compressor rotor wheel and method of making same |
4348041, | Jan 25 1978 | Hitachi, Ltd. | Butt welded tubular structure of austenite stainless steel |
4406698, | Apr 28 1980 | Tokyo Shibaura Denki Kabushiki Kaisha | Martensitic stainless cast steel having high cavitation erosion resistance |
4429019, | Jan 03 1980 | Bulten-Kanthal AB | Heat-resistant machine component |
4499158, | Mar 05 1980 | Hitachi, Ltd. | Welded structural member having high erosion resistance |
4585917, | Feb 28 1983 | Ishikawajima-Harima Jukogyo Kabushiki Kaisha | Method for relieving residual stresses by build-up welding over outer surface of pipe |
4588869, | Feb 28 1983 | Ishikawajima-Harima Jukogyo Kabushiki Kaisha | Method for relieving residual stresses by controlling weld heat input |
4624402, | Jan 18 1983 | DUKE ENGINEERING & SERVICES, INC | Method for applying an overlay weld for preventing and controlling stress corrosion cracking |
4633554, | Aug 08 1985 | Siemens Westinghouse Power Corporation | Method for repairing a steam turbine or generator rotor |
4657171, | Jun 13 1985 | General Electric Company | Repair of a member having a projection |
4710103, | Jun 18 1985 | Alstom | Method for fastening blades on the periphery of the rotor body of a steam turbine and the turbo-machine produced by the method |
4786772, | Nov 07 1986 | Ishikawajima-Harima Heavy Industries Co., Ltd. | Induction heating coil for heat-treating metallic tubes |
4813806, | Sep 03 1985 | Mitsubishi Jukogyo Kabushiki Kaisha | Welding beveling of T-joint |
4832993, | Mar 09 1987 | Alsthom | Method of applying a protective coating to a titanium alloy blade, and a blade obtained thereby |
DE2122613, | |||
EP163828, | |||
EP207259, | |||
EP332875, | |||
JP2127990, | |||
JP5542129, | |||
JP5572612, | |||
JP56163091, | |||
JP5645269, | |||
JP5758992, | |||
JP59110723, | |||
JP5950991, | |||
JP62101393, | |||
JP62282796, | |||
JP63157769, | |||
JP63295802, | |||
JP6354480, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Jan 26 1998 | Siemens Westinghouse Power Corporation | (assignment on the face of the patent) | / | |||
Sep 29 1998 | CBS CORPORATION, FORMERLY KNOWN AS WESTINGHOUSE ELECTRIC CORP | Siemens Westinghouse Power Corporation | NUNC PRO TUNC ASSIGNMENT SEE DOCUMENT FOR DETAILS | 009827 | /0570 | |
Aug 01 2005 | Siemens Westinghouse Power Corporation | SIEMENS POWER GENERATION, INC | CHANGE OF NAME SEE DOCUMENT FOR DETAILS | 016996 | /0491 |
Date | Maintenance Fee Events |
Date | Maintenance Schedule |
Feb 26 2005 | 4 years fee payment window open |
Aug 26 2005 | 6 months grace period start (w surcharge) |
Feb 26 2006 | patent expiry (for year 4) |
Feb 26 2008 | 2 years to revive unintentionally abandoned end. (for year 4) |
Feb 26 2009 | 8 years fee payment window open |
Aug 26 2009 | 6 months grace period start (w surcharge) |
Feb 26 2010 | patent expiry (for year 8) |
Feb 26 2012 | 2 years to revive unintentionally abandoned end. (for year 8) |
Feb 26 2013 | 12 years fee payment window open |
Aug 26 2013 | 6 months grace period start (w surcharge) |
Feb 26 2014 | patent expiry (for year 12) |
Feb 26 2016 | 2 years to revive unintentionally abandoned end. (for year 12) |