An apparatus to aid in the accurate installation of a frame by establishing a required gap and alignment is disclosed. The apparatus comprises a block of material with pre-determined dimensions related to the standard or custom dimensions of the frame and standard or custom dimensions of a subsequent stud and dry wall to be installed. The block of material has a slot running along the length of at least one side with the slot having a pre-determined depth and width corresponding to standard or custom dimensions of an outer lip of the frame to be installed for fitting the block of material onto the outer lip. A securing system for temporarily securing the block of material to the outer lip is also provided. The slot is offset from an edge of the block of material by a distance corresponding to the required gap and alignment to be established.
|
9. A system for installing a frame including:
a block with a slot in a side of said block, wherein said slot is along the entire length of said side of said block; a wall track installed on a floor; and a frame with a lip, wherein said up is positioned within said slot and said block maintains a predetermined gap between said lip and said wall track.
7. A system for installing a frame including:
a block with a slot in a side of said block; a wall track installed on a floor; a frame with a lip, wherein said lip is positioned within said slot and said block maintains a predetermined gap between said lip and said wall track; and a drywall panel, wherein said predetermined gap equals a thickness of said drywall panel.
8. A system for installing a frame including:
a block with a slot in a side of said block; a wall track installed on a floor; and a frame with a lip, wherein said lip is positioned within said slot and said block maintains a predetermined gap between said lip and said wall track; a wall panel with a thickness of ½", ⅝", ¾", 1", 1-¼", wherein said predetermined gap equals said thickness of said wall panel.
1. Apparatus for installing a frame with a lip adjacent to a wall track comprising:
a block of material; a slot running along a length of at least one side of said block of material; and a securing system attached to said block material to temporarily secure said block of material, along said slot, to said lip of said frame, wherein a portion of said block material is positioned between said lip of said frame and the wall track.
4. A system for installing a frame including:
a block with a slot in a side of said block; a wall track installed on a floor; and a frame with a lip, wherein said lip is positioned within said slot and said block maintains a predetermined gap between said lip and said wall track, a wall panel, wherein said predetermined gap is at least as large as a thickness of said wall panel and a portion of said wall panel is installed within said gap.
2. The apparatus of
3. The apparatus of
6. The system of
|
The applicants claim priority based on provisional application No. 60/316,947 filed Aug. 30, 2001, the complete subject matter of which is incorporated herein by reference in its entirety.
[Not Applicable]
[Not Applicable]
Certain embodiments of the present invention relate to the field of construction, particularly, the installation of metal frames for doors and windows by a carpenter. When metal doorframes or metal windows are to be installed, it is necessary for the carpenter to establish the proper gap between the vertical frame supports and the metal track on the floor to allow space for subsequent installation of dry wall material. Also, alignment of the vertical metal stud to the metal frame is required before affixing the stud to the metal frame. Typically, measurements or calculations of distances with a tape measure and/or other tools is required. Also, the metal stud would need to be somehow clamped and secured in the correct position before affixing to the frame. It is desired to eliminate the need for these steps, minimizing installation time and maximizing craftsmanship of frame installation.
Further limitations and disadvantages of conventional and traditional approaches will become apparent to one of skill in the art, through comparison of such systems with embodiments of the present invention as set forth in the remainder of the present application with reference to the drawings.
An embodiment of the present invention provides for the accurate installation of a frame such as a door frame or a window frame.
An apparatus is disclosed to aid in the accurate installation of a frame by establishing a desired gap and alignment. The apparatus comprises a block of material with pre-determined dimensions related to the standard or custom dimensions of the frame and standard or custom dimensions of a subsequent stud and dry wall to be installed. The block of material has a slot running along the length of at least one side with the slot having a pre-determined depth and width corresponding to standard or custom dimensions of an outer lip of the frame to be installed for fitting the block of material onto the outer lip. A securing system for temporarily securing the block of material to the outer lip is also provided. The slot is offset from an edge of the block of material by a distance corresponding to the required gap and alignment to be established.
Certain embodiments of the present invention afford an approach to accurately install a door frame or window frame using at least one single block of material with certain standard or custom dimensions to provide a proper gap and alignment.
An embodiment of the present invention allows two measuring tasks to be completed accurately and more efficiently without the use of measuring tapes, markings, etc. The first task is that of quickly establishing the proper gap between the vertical doorframe supports 130 and the metal track 140 on the floor. The second task is that of quickly aligning the vertical metal stud 150 in order to affix it to the metal doorframe 130.
Metal track 140 is used as a guide for wall construction. Metal track 140 is installed on a floor up to the location of where a door will be positioned. A space the width of a doorframe is left between the two runs of metal track 140. The metal doorframe 130 may be positioned inside the opening. A dry wall thickness is identified, which is usually a pre-determined decision. The tool 100 accommodates ½, ⅝, ¾, 1¼ (double ⅝), and double half inch thick dry wall. The corresponding measurement is identified by markings on the tool and the appropriate slot 110 to be used is selected. The slot 110 in the tool 100 is slid onto the outside lip 135 of the doorframe 130 where the floor and frame adjoin, such that the appropriate gap is maintained between the doorframe 130 and the metal floor track 140. Each side of the doorframe 130 uses this tool 100 to establish the appropriate gap, and then the doorframe 130 is secured to the floor substrate using standard methods. Later in the construction process, dry wall is inserted into this gap created between the metal track 140 and doorframe 130.
After establishing the proper gap between the doorframe 130 and metal track 140, a metal stud 150 is installed to further secure the doorframe 130. To do this, the same slot 110 that was used to create the gap between the metal track 140 and doorframe 130 is selected on two tools 100. The tools 100 are slid onto the outside lip 135 of the metal doorframe 130 on both the entrance and exit sides. The tools 100 are moved up the doorframe 130 to the top door clip 170. The tools 100 preferably are to be parallel so as to create a pre-determined space between them. The magnets in the slots 110 keep the tools 100 in place until the work is finished. After positioning the tools 100 in the proper location, the metal door stud 150 is positioned in the fixed space between the two tools 100. This allows the door stud 150 to fit tightly into the space, establishing an alignment, and the metal stud 150 may then be affixed to the metal doorframe 130. The steps are repeated on the left and right sides of the doorframe 130.
Additionally, in an embodiment of the present invention, a numbered scale 180 is included on the outside faces of the tool 100. The numbered scale 180 may be used, for example, in conjunction with a laser tool to establish a constant elevation of the tops of multiple door frames 130 along a wall or between walls. If the block tool 100 is aligned, for example, flush to the head of a frame, a laser or other distance leveling device may be used to level a long corridor of doors using block tools 100 as a stable reference point instead of a tape measure or a stick rule which may vary and cannot easily be kept in position.
In summary, certain embodiments of the present invention afford an approach to accurately install a door frame or window frame using a rectangular block of material of certain predetermined dimensions and having slots cut into the block of material having certain other predetermined dimensions.
While the invention has been described with reference to certain embodiments, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted without departing from the scope of the invention. In addition, many modifications may be made to adapt a particular situation or material to the teachings of the invention without departing from its scope. Therefore, it is intended that the invention not be limited to the particular embodiment disclosed, but that the invention will include all embodiments falling within the scope of the appended claims.
Wagner, John, Ratliff, Joseph, Zochowski, Richard
Patent | Priority | Assignee | Title |
10024067, | Apr 30 2015 | Door assembly installation tool | |
7240436, | Jan 20 2006 | SHULTZ, BRAD | Door frame alignment device |
7299554, | Jun 18 2004 | Hinge base plate mounting tool for face frame hinges | |
7513049, | Jan 08 2007 | Carpentry marking tool | |
7591073, | Apr 18 2008 | PL2, LLC | Device and method for measuring door gaps |
7730622, | Aug 02 2006 | Structural surface measuring and aligning apparatus and method | |
7743517, | May 19 2009 | Guide for establishing reveal on door and window frames during molding installation | |
7849652, | Nov 09 2006 | USG INTERIORS, LLC | Suspended ceiling with measurement indicia |
7975395, | Dec 15 2004 | SLK Development Group, LLC | Hand-held level and plumb tool |
8893394, | Mar 19 2012 | Carpentry guide tool for making consistent reveals | |
9273510, | Apr 18 2013 | Systems, devices, and/or methods for managing door frames |
Patent | Priority | Assignee | Title |
2636527, | |||
3852935, | |||
4925074, | Apr 21 1989 | Electric Power Research Institute, Inc.; ELECTRIC POWER RESEARCH INSTITUTE, INC , A CORP OF D C | Welding tool |
4989336, | Jul 28 1989 | Trim positioning device | |
5388813, | Oct 25 1993 | Ceiling clamp | |
5737844, | Apr 15 1996 | Trim gauge | |
5758466, | Apr 10 1997 | ENVIRO-LOGS INTERNATIONAL, INC | Snap-together structure |
5775036, | Apr 15 1996 | Motorola, Inc | Alignment of objects |
5775045, | Jan 18 1997 | Door frame guard | |
5813125, | Aug 27 1996 | Self holding leveling square | |
5913546, | Dec 29 1997 | Flight-X Corporation | Stud alignment tool and method of use |
6327786, | Mar 31 1999 | Carpenters square with elevation attachment | |
6532674, | Mar 20 2001 | Marking tool for finish carpentry | |
6637158, | Sep 15 2000 | ENDURA PRODUCTS, INC | Leak resistant entryway assembly with anti-wicking weather strips |
20020170189, | |||
20030005589, | |||
20040000061, | |||
JP10037580, |
Executed on | Assignor | Assignee | Conveyance | Frame | Reel | Doc |
Sep 09 2002 | ZOCHOWSKI, RICHARD | WAGNER, JOHN | ASSIGNMENT OF ASSIGNORS INTEREST SEE DOCUMENT FOR DETAILS | 013394 | /0174 |
Date | Maintenance Fee Events |
Apr 21 2008 | M2551: Payment of Maintenance Fee, 4th Yr, Small Entity. |
Apr 18 2012 | M2552: Payment of Maintenance Fee, 8th Yr, Small Entity. |
Jun 03 2016 | REM: Maintenance Fee Reminder Mailed. |
Oct 26 2016 | EXP: Patent Expired for Failure to Pay Maintenance Fees. |
Date | Maintenance Schedule |
Oct 26 2007 | 4 years fee payment window open |
Apr 26 2008 | 6 months grace period start (w surcharge) |
Oct 26 2008 | patent expiry (for year 4) |
Oct 26 2010 | 2 years to revive unintentionally abandoned end. (for year 4) |
Oct 26 2011 | 8 years fee payment window open |
Apr 26 2012 | 6 months grace period start (w surcharge) |
Oct 26 2012 | patent expiry (for year 8) |
Oct 26 2014 | 2 years to revive unintentionally abandoned end. (for year 8) |
Oct 26 2015 | 12 years fee payment window open |
Apr 26 2016 | 6 months grace period start (w surcharge) |
Oct 26 2016 | patent expiry (for year 12) |
Oct 26 2018 | 2 years to revive unintentionally abandoned end. (for year 12) |